cc/td/doc/product/ong/15327/r34userd
hometocprevnextglossaryfeedbacksearchhelp
PDF

Table Of Contents

Install Hardware

Before You Begin

Required Tools and Equipment

lncluded Materials

User-Supplied Materials

NTP-B1 Unpack and Inspect the ONS 15327 Shelf Assembly

DLP-B1 Unpack and Verify the Shelf Assembly

DLP-B2 Inspect the Shelf Assembly

NTP-B2 Install the Shelf Assembly

DLP-B3 Reverse the Mounting Bracket to Fit a 19-inch Rack

DLP-B5 Mount the ONS 15327 in a Rack

DLP-B7 Mount Multiple Shelf Assemblies in a Rack

DLP-B329 Install the Tie-Down Bar

NTP-B216 Install the Mechanical Interface Cards

NTP-B6 Install the Power and Ground

DLP-B16 Connect the Office Ground to the ONS 15327

DLP-B17 Connect Office Power to the ONS 15327 Shelf (Screw-Lock Power Connector)

DLP-B18 Turn On and Verify Office Power

DLP-B30 Install Ferrites on Power Cabling

NTP-B7 Install the Fan-Tray Assembly

NTP-B217 Install the XTCs

NTP-B218 Install the Optical and Ethernet Cards

DLP-D4 Install SFP Connectors on G1000-2 Cards

DLP-D6 Remove SFP Connectors from G1000-2 Cards

NTP-B219 Remove and Replace a Card

DLP-B320 Delete a Card

DLP-B247 Change an Optical Card

NTP-B115 Preprovision a Slot

NTP-B8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

DLP-B321 Install External Alarm Cables

DLP-B322 Install Timing Cables

DLP-B323 Install the Serial Cable for TL1 Craft Interface

NTP-B220 Install the Electrical Cables

DLP-B324 Install DS-1 Champ Cables on a MIC

DLP-B325 Install Coaxial Cable With BNC Connectors

DLP-B326 Route Electrical Cables

NTP-B221 Install Optical Cables

DLP-B327 Install Fiber-Optic Cables on the LGX Interface

DLP-B42 Install Fiber-Optic Cables on OC-N Cards

DLP-B43 Install Fiber-Optic Cables for UPSR Configurations

DLP-B44 Install Fiber-Optic Cables for BLSR Configurations

DLP-B46 Route Fiber-Optic Cables

NTP-B13 Perform the Shelf Installation Acceptance Test

DLP-B33 Measure Voltage


Install Hardware


This chapter provides procedures for installing the Cisco ONS 15327 shelf, cards, and fiber-optic cable. To view a summary of the tools and equipment required for installation, see the "Required Tools and Equipment" section.

Before You Begin

This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs).

1. 1 Unpack and Inspect the ONS 15327 Shelf Assembly—Complete this procedure before continuing with the "2 Install the Shelf Assembly" procedure.

2. 2 Install the Shelf Assembly—Complete this procedure to install the shelf assembly in a rack before continuing with the "216 Install the Mechanical Interface Cards" procedure.

3. 216 Install the Mechanical Interface Cards—Complete this procedure to install the Mechanical Interface cards (MICs) before continuing with the "6 Install the Power and Ground" procedure.

4. 6 Install the Power and Ground—Complete this procedure before continuing with the "7 Install the Fan-Tray Assembly" procedure.

5. 7 Install the Fan-Tray Assembly—Complete this procedure to install the fan-tray assembly in the shelf before continuing with the "217 Install the XTCs" procedure.

6. 217 Install the XTCs—Complete this procedure to install the Cross-Connect Timing and Control (XTC) cards.

7. 218 Install the Optical and Ethernet Cards—As needed, complete this procedure to install optical and Ethernet cards.

8. 219 Remove and Replace a Card—As needed, complete this procedure to remove and replace an ONS 15327 card.

9. 115 Preprovision a Slot—As needed, complete this procedure to preprovision any empty card slot with a card that will be installed later.

10. 8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections—Complete this procedure to install cables for alarms, timing, and LAN connections.

11. 220 Install the Electrical Cables—Complete this procedure to connect and route cables that will carry electrical traffic.

12. 221 Install Optical Cables—Complete this procedure to connect and route cables that will carry optical traffic.

13. 13 Perform the Shelf Installation Acceptance Test—Complete this procedure to determine if you have correctly completed all other procedures in the chapter.


Warning Only trained and qualified personnel should be allowed to install, replace, or service this equipment.



Warning The ONS 15327 is intended for installation in restricted access areas. A restricted access area is where access can only be gained by service personnel through the use of a special tool, lock, key, or other means of security. A restricted access area is controlled by the authority responsible for the location.



Warning Ultimate disposal of this product should be handled according to all national laws and regulations.



Note The ONS 15327 is designed to comply with GR-1089-CORE Type 2 and Type 4. Install and operate the ONS 15327 only in environments that do not expose wiring or cabling to the outside plant. Acceptable applications include Central Office Environments (COEs), Electronic Equipment Enclosures (EEEs), Controlled Environment Vaults (CEVs), huts, and Customer Premise Environments (CPEs).



Note The Cisco ONS 15327 is intended for use with telecommunications equipment only.


Required Tools and Equipment

You will need the following tools and equipment to install and test the ONS 15327.

lncluded Materials

These materials are shipped with the ONS 15327. The number in parentheses provides the quantity of the item included in the package.

#12-24 x 1/2 pan head Phillips mounting screws (4)

#10-32 x 3/8 pan head Phillips power lug screws (2)

#12 AWG dual hole 5/8 in. spaced grounding lug

Electrostatic discharge (ESD) wrist strap with 1.8 m (6 ft.) coil cable

Screw-lock power connector

Terminal-lug power connector

Terminal lugs (4)

Terminal lug screws (4)

Straight DS-1 cable

Tie-down bar (optional) (15327-TIE-BAR-19 for a 19-inch rack or 15327-TIE-BAR-23 for a 23-inch rack)

Cable storage tray and screws (4) (optional)

User-Supplied Materials

These materials and tools are required but are not supplied with the ONS 15327.

Equipment rack (22 inches total width for a 19-inch rack; 26 inches total width for a 23-inch rack)

Fuse panel

Copper power cable (from fuse and alarm panel to assembly), #12-16 AWG

The National Electrical Code recommends #12-14 AWG power cable

Ground cable, #12 AWG stranded (minimum)

Alarm cable, CAT-5 terminated with RJ-45 for all alarm connections

Building Integrated Timing Supply (BITS) clock cable, 100-ohm #22 or #24 (0.51 mmІ or 0.64 mmІ), twisted-pair, T1-type, shielded AWG wire

Serial cable, DB-9 connectors

Single-mode SC fiber jumpers with UPC polish (55 dB or better) for OC12 and OC-48 cards and fiber jumpers with LC connectors for the OC-3 card

Shielded ABAM cable terminated with Champ connectors for DS-1 ports with #22 or #24 AWG ground wire (optional)

Shielded coaxial cable terminated with BNC connectors for DS-3 ports

Tie wraps and/or lacing cord

Labels

Tools Needed

#2 Phillips screw driver

Medium slot head screw driver

Small slot head screw driver

Wire cutters

Wire strippers

Crimp tool

Needle nose pliers (for bail locks on Champ connectors)

Test Equipment

Volt meter

Power meter (for use with fiber optics only)

Bit Error Rate (BER) tester, DS-1 and DS-3


Note In this chapter, the terms "ONS 15327" and "shelf assembly" are used interchangeably. In the installation context, these terms have the same meaning. Otherwise, shelf assembly refers to the physical steel enclosure that holds cards and connects power, and ONS 15327 refers to the entire system, both hardware and software.


NTP-B1 Unpack and Inspect the ONS 15327 Shelf Assembly

Purpose

This procedure describes how to unpack the ONS 15327 and verify the contents.

Tools/Equipment

None

Prerequisite Procedures

None

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Step 1 Complete the "DLP-B1 Unpack and Verify the Shelf Assembly" task.

Step 2 Complete the "DLP-B2 Inspect the Shelf Assembly" task.

Step 3 Continue with the "2 Install the Shelf Assembly" procedure.

Stop. You have completed this procedure.


DLP-B1 Unpack and Verify the Shelf Assembly

Purpose

This task removes the shelf assembly from the package.

Tools/Equipment

None

Prerequisite Procedures

None

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Step 1 When you receive the ONS 15327 system equipment at the installation site, open the top of the box. The Cisco Systems logo designates the top of the box.

Step 2 Remove the foam inserts from the box. The box contains the ONS 15327 shelf (wrapped in plastic) and a smaller box containing items needed for installation.

Step 3 To remove the shelf, grasp both sides of the shelf and slowly lift it out of the box.

Step 4 Open the smaller box containing installation materials, and verify that you have all items listed in the "lncluded Materials" section.


Note The fan-tray assembly is shipped separately.


Step 5 Return to your originating procedure (NTP).


DLP-B2 Inspect the Shelf Assembly

Purpose

This task verifies that all parts of the shelf assembly are in good condition.

Tools/Equipment

None

Prerequisite Procedures

1 Unpack and Verify the Shelf Assembly

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Step 1 Verify the following:

Pins are not bent or broken

Frame is not bent

Step 2 If the pins are bent or broken, or the frame is bent, call your Cisco sales engineer for a replacement.

Step 3 Return to your originating procedure (NTP).


NTP-B2 Install the Shelf Assembly

Purpose

This procedure describes how to reverse the mounting bracket and mount shelf assemblies in a rack.

Tools/Equipment

#2 Phillips screwdriver

Medium slot-head screwdriver

Small slot-head screwdriver

Two set screws (48-1003-XX)

Prerequisite Procedures

1 Unpack and Inspect the ONS 15327 Shelf Assembly

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Warning To prevent the equipment from overheating, do not operate it in an area that exceeds the maximum recommended ambient temperature of 131°F (55°C). To prevent airflow restriction, allow at least 3 inches (7.6 cm) of clearance around the ventilation openings.



Warning The ONS 15327 must have 1 inch of airspace below the installed shelf assembly to allow air flow to the fan intake. The air ramp (the angled piece of sheet metal on top of the shelf assembly) provides this spacing and should not be modified in any way.



Step 1 Complete the "DLP-B3 Reverse the Mounting Bracket to Fit a 19-inch Rack" task if you need to convert from a 23-inch to a 19-inch rack.

Step 2 Complete the necessary rack mount task:

5 Mount the ONS 15327 in a Rack

7 Mount Multiple Shelf Assemblies in a Rack

Step 3 As needed, complete the "DLP-B329 Install the Tie-Down Bar" task.


Note You can also install a cable storage drawer in the ONS 15327 rack. This drawer provides room to store up to five feet of slack and can provide a diverse cable route for redundant power feeds and cables. See the "NTP-B223 Install the Fiber-Optic Cable Storage Drawer" procedure on page D-2.


Step 4 Continue with the "216 Install the Mechanical Interface Cards" procedure.

Stop. You have completed this procedure.


DLP-B3 Reverse the Mounting Bracket to Fit a 19-inch Rack

Purpose

This task installs the mounting bracket to convert a 23-inch rack to a 19-inch rack.

Tools/Equipment

#2 Phillips screwdriver

Medium slot-head screwdriver

Small slot-head screwdriver

Prerequisite Procedures

None

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Caution Use only the fastening hardware provided with the ONS 15327 to prevent loosening, deterioration, and electromechanical corrosion of the hardware and joined material.


Caution When mounting the ONS 15327 in a frame with a non-conductive coating (such as paint, lacquer, or enamel) use the thread-forming screws provided with the ONS 15327 shipping kit or remove the coating from the threads to ensure electrical continuity.


Step 1 Remove the screws that attach the mounting bracket to the side of the shelf assembly.

Step 2 Flip the detached mounting bracket upside down.

Text imprinted on the mounting bracket will now also be upside down.

Step 3 Place the widest side of the mounting bracket flush against the shelf assembly (see Figure 1-1).

The narrow side of the mounting bracket should be towards the front of the shelf assembly. Text imprinted on the mounting bracket should be visible and upside down.

Step 4 Align the mounting bracket screw holes against the shelf assembly screw holes.

Step 5 Insert the screws that were removed in Step 1 and tighten them.

Step 6 Repeat the task for the mounting bracket on the opposite side.

Figure 1-1 Reversing the Mounting Brackets (23-Inch Position to 19-Inch Position)

Step 7 Return to your originating procedure (NTP).


DLP-B5 Mount the ONS 15327 in a Rack

Purpose

This task allows one person to mount the shelf assembly in a rack.

Tools/Equipment

Two sets of #12-24 mounting screws

# 2 Phillips screwdriver

Fuse and alarm panel, if not installed

Prerequisite Procedures

3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Note Mounting the ONS 15327 in a rack requires a minimum of 5.2 inches of vertical rack space (plus 1 inch for air flow). To ensure the mounting is secure, use two to four #12-24 mounting screws for each side of the shelf assembly.



Step 1 Verify that the proper fuse and alarm panel has been installed in the top mounting space. If a fuse and alarm panel has not been installed, you must install one according to manufacturer's instructions. A fuse panel with two 10-amp fuses per shelf is required for Power A and B feeds.

Step 2 Ensure that the shelf assembly is set for the desired rack size (either 19 or 23 inches).

Step 3 Lift the shelf assembly to the desired rack position and set it on the set screws.

Step 4 Align the screw holes on the mounting ears with the mounting holes in the rack.

Step 5 Using the Phillips screwdriver, install one mounting screw in each side of the assembly.

Step 6 When the shelf assembly is secured to the rack, install the remaining mounting screws.

Step 7 Return to your originating procedure (NTP).


DLP-B7 Mount Multiple Shelf Assemblies in a Rack

Purpose

This task installs multiple shelf assemblies in a rack.

Tools/Equipment

#2 Phillips screwdriver

Medium slot-head screwdriver

Small slot-head screwdriver

Prerequisite Procedures

3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Note The ONS 15327 must have one inch of air space below the installed shelf assembly to allow air flow to the fan intake. If a second ONS 15327 is installed underneath a shelf assembly, the air ramp on top of the bottom shelf assembly provides the desired space. However, if the ONS 15327 is installed above third-party equipment, you must provide a minimum spacing of one inch between the third-party shelf assembly and the bottom of the ONS 15327. The third-party equipment must not vent heat upward into the ONS 15327.



Step 1 Verify that the proper fuse and alarm panel has been installed in the top mounting space. If a fuse and alarm panel is not present, you must install one according to manufacturer instructions. A fuse panel with two 10-amp fuses per shelf is required for Power A and B feeds.

Step 2 Mount the first ONS 15327 directly below the fuse and alarm panel using the "DLP-B5 Mount the ONS 15327 in a Rack" task.


Note If you want to install a tie-down bar on the rack, be sure to leave 1 RU between each ONS 15327 you plan to install and the tie-down bar.


Step 3 Repeat the task with the remaining ONS 15327s (up to 12 shelves can fit in a rack).

Step 4 Return to your originating procedure (NTP).


DLP-B329 Install the Tie-Down Bar

Purpose

This task installs the tie-down bar used to secure cabling on the ONS 15327. The tie-down bar can be used to provide a diverse path for redundant power feeds and cables.

Tools/Equipment

Tie-down bar

Screws (4)

Prerequisite Procedures

5 Mount the ONS 15327 in a Rack

Required/As Needed

As Needed

Onsite/Remote

Onsite

Security Level

None



Step 1 Align the ends of the tie-down bar with the four screw holes located 1 RU below the ONS 15327.

Figure 1-2 shows the tie-down bar, the ONS 15327, and the rack.

Figure 1-2 Tie-Down Bar

Step 2 Install the four screws into the rack.

Step 3 Return to your originating procedure (NTP).


NTP-B216 Install the Mechanical Interface Cards

Purpose

This procedure installs the two Mechanical Interface cards (MICs) in Slots 7 and 8.

Tools/Equipment

None

Prerequisite Procedures

2 Install the Shelf Assembly

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Warning During this procedure, wear grounding wrist straps to avoid ESD damage to the card. Do not directly touch the backplane with your hand or any metal tool to avoid the risk of shock.



Step 1 Install MIC A in Slot 8:

a. Open the card ejectors.

b. Slide the card along the guide rails into the slot.

c. Close the ejectors.

d. Lock the cards into place by tightening the ejector locking screws.

The slots are keyed to ensure that cards are installed in the correct slots. Figure 1-3 shows the location and number of each slot.

Figure 1-3 ONS 15327 Slot Numbering

Step 2 If you require redundant power, more than 14 DS-1s, or you are using DS-3s, install MIC B in Slot 7.


Warning Always make sure power is disconnected before removing MICs from the ONS 15327.


Step 3 Continue with the "6 Install the Power and Ground" procedure.

Stop. You have completed this procedure.


NTP-B6 Install the Power and Ground

Purpose

This procedure describes how to install power feeds and how to ground the ONS 15327.

Tools/Equipment

Ground cable, #12 AWG stranded (minimum)

Copper power cable (from fuse and alarm panel to assembly), #12-16 AWG (the National Electrical Code recommends #12-14 AWG power cable)

Prerequisite Procedures

216 Install the Mechanical Interface Cards

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Warning Shut off the power from the power source or turn off the breakers before beginning work.



Warning This equipment is intended to be grounded. Ensure that the host is connected to earth ground during normal use.



Warning Do not mix conductors of dissimilar metals in a terminal or splicing connector where physical contact occurs (such as copper and aluminum, or copper and copper-clad aluminum), unless the device is suited for the purpose and conditions of use.



Warning Connect the ONS 15327 only to a DC power source that complies with the safety extra-low voltage (SELV) requirements in IEC 60950-based safety standards.



Warning The ONS 15327 relies on the protective devices in the building installation to protect against short circuit, overcurrent, and grounding faults. Ensure that the protective devices are properly rated to protect the system, and that they comply with national and local codes.



Warning A readily accessible two-poled disconnect device must be incorporated in the fixed wiring.



Warning When installing redundant power feeds, do not use aluminum conductors.



Warning If you use redundant power leads to power the ONS 15327 disconnecting one lead will not remove power from the node.



Caution Always use the supplied ESD wristband when working with a powered ONS 15327. Plug the wristband cable into the ESD jack located between the top high-speed and XTC slots.


Step 1 Verify that the proper fuse panel is installed (20-amp fuse per shelf minimum). If not, install one according to manufacturer's instructions.

Step 2 Ensure that the mechanical interface cards (MICs) are installed. See the "216 Install the Mechanical Interface Cards" procedure if necessary.

Step 3 Complete the "DLP-B16 Connect the Office Ground to the ONS 15327" task.

Step 4 Complete the "DLP-B17 Connect Office Power to the ONS 15327 Shelf (Screw-Lock Power Connector)" task.

Step 5 Complete the "DLP-B18 Turn On and Verify Office Power" task.

Step 6 Complete the "DLP-B30 Install Ferrites on Power Cabling" task.

Step 7 Continue with the "7 Install the Fan-Tray Assembly" procedure.

Stop. You have completed this procedure.


DLP-B16 Connect the Office Ground to the ONS 15327

Purpose

This task connects ground to the ONS 15327 shelf.

Tools/Equipment

#2 Phillips screwdriver

Medium slot-head screwdriver

Small slot-head screwdriver

Screws

Power cable (from fuse and alarm panel to assembly), #10 AWG, copper conductors, 194°F [90°C])

Ground cable #6 AWG stranded

Listed pressure terminal connectors such as ring and fork types; connectors must be suitable for #10 AWG copper conductors

Prerequisite Procedures

None

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Step 1 Verify that the office ground cable (#6 AWG stranded) is connected to the top of the rack according to local site practice.

Step 2 Attach one end of the shelf ground cable (#10 AWG) to the ground connection point located on the left-hand side panel as you face the ONS 15327.


Note When terminating a frame ground, use the kep-nut provided with the ONS 15327 and tighten it to a torque specification of 31 in-lbs. The kep-nut provides a frame ground connection that minimizes the possibility of loosening caused by rotation during installation and maintenance activity. The type of prevention the kep-nut provides for the frame ground connection is inherently provided by the terminal block for battery and battery return connections.


Step 3 Attach the other end of the shelf ground cable to the rack.

Step 4 Return to your originating procedure (NTP).


DLP-B17 Connect Office Power to the ONS 15327 Shelf (Screw-Lock Power Connector)

Purpose

This task connects power to the ONS 15327 shelf. You must install this power connector if you plan to install the right-angle DS-1 cable.

Tools/Equipment

#2 Phillips screwdriver

Medium slot-head screwdriver

Small slot-head screwdriver

Wire wrapper

Wire cutters

Wire strippers

Crimp tool

Fuse panel

Screw-lock power connector

Power cable (from fuse and alarm panel to assembly), #10 AWG, copper conductors, 194°F [90°C])

Ground cable #6 AWG stranded

Listed pressure terminal connectors such as ring and fork types; connectors must be suitable for #10 AWG copper conductors

Prerequisite Procedures

16 Connect the Office Ground to the ONS 15327

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Warning Do not apply power to the ONS 15327 until you complete all installation steps and check the continuity of the -48 VDC and return.



Caution Before you make any crimp connections, coat all bare conductors (battery, battery return, and frame ground) with an appropriate antioxidant compound. Bring all unplated connectors, braided strap, and bus bars to a bright finish, then coat with an antioxidant before you connect them. You do not need to prepare tinned, solder-plated, or silver-plated connectors and other plated connection surfaces in this manner, but always keep them clean and free of contaminants.


Note You must install this power connector if you plan to install the right-angle DS-1 cable.



Note This procedure explains how to install the screw-lock power connector. To install the terminal-lug power connector also included with the ONS 15327, see the "NTP-B222 Connect Office Power to the ONS 15327 Shelf (Terminal-Lug Power Connector)" procedure on page D-4.



Note If you encounter problems with the power supply, refer to the Cisco ONS 15327 Troubleshooting Guide.



Step 1 Connect the office power according to the fuse panel engineering specifications.

Step 2 Measure and cut the cables as needed to reach the ONS 15327 from the fuse panel.

Step 3 Dress the power according to local site practice.


Warning When installing the ONS 15327, the ground connection must always be made first and disconnected last.


Step 4 Strip .22 inches of insulation from all power cables that you connect to the ONS 15327 power connectors.


Warning Do not expose more than .22 inches of bare wire on power cables.


Step 5 If the power connector is already installed, remove it from the MIC by grasping it with your fingers and gently pulling it. If you cannot remove it easily, you can use a pair of needle nose pliers and grab it by the center of the channel. Figure 1-4 shows the MIC power connector being removed.

Figure 1-4 Removing the MIC Power Connector

Step 6 Remove the cable fastening screws, which are the screws on the top of the connector that become visible when the connector is removed.

Step 7 Insert the (black) return (RTN) wire into the right connector slot. Figure 1-5 shows a power cable being inserted into the MIC power connector.

Figure 1-5 Inserting a Power Cable into the MIC Power Connector

Step 8 Replace the cable fastening screw for the return (RTN) wire and tighten with a small slot-head screwdriver.

Step 9 Insert the battery (red) wire into the left (-48V) connector slot.

Step 10 Replace the cable fastening screw for the battery (-48V) wire and tighten it with the screwdriver.

Step 11 Insert the connector back into the slot on the MIC and tighten the screws with the screwdriver. Figure 1-6 shows the MIC power connector being installed.

Figure 1-6 Installing the MIC Power Connector

Step 12 Use a small flat-head screwdriver to open the return (RTN) terminal and insert the return lead.

Step 13 If you use redundant power feeds, repeat Steps 5 through 12 on the other MIC.


Caution In case a power cable is damaged or cut, Cisco recommends that you diversely route redundant power leads along different paths. If you installed the tie-down bar, you can run one power lead across the tie-down bar and secure it using tie-wraps or other site-specific methods. You should route the other power cable in the opposite direction.

Figure 1-7 shows redundant power connected to an ONS 15327.

Figure 1-7 Redundant Power Connections

Step 14 Return to your originating procedure (NTP).


DLP-B18 Turn On and Verify Office Power

Purpose

This task measures the power to verify correct power and returns.

Tools/Equipment

Voltmeter

Prerequisite Procedures

16 Connect the Office Ground to the ONS 15327

17 Connect Office Power to the ONS 15327 Shelf (Screw-Lock Power Connector)

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Step 1 Using a voltmeter, verify the office battery and ground at the following points on the fuse and alarm panel:

a. To verify the power, place the black test lead of the voltmeter to the frame ground. Place the red test lead on the A-side connection and verify that it is between -42 VDC and -57 VDC. Place the red test lead on the B-side connection and verify that it is between -42 VDC and -57 VDC.


Note The voltages -42 VDC and -57 VDC are the minimum and maximum amperages required to power the chassis.


b. To verify the ground, place the black test lead of the voltmeter to the frame ground. Place the red test lead on the A-side return ground and verify that no voltage is present. Place the red test lead on the B-side return ground and verify that no voltage is present.

Step 2 Insert a 10-amp fuse into the fuse position according to site practice.

Step 3 Using a voltmeter, verify the shelf for -48 VDC battery and ground:

a. To verify the A-side of the shelf, place the black lead of the voltmeter to the frame ground. Place the red test lead to the BAT1 (A-side battery connection) red cable. Verify it reads between -42 VDC and -57 VDC. Then place the red test lead of the voltmeter to the RET1 (A-side return ground) black cable and verify that no voltage is present.

b. To verify the B-side of the shelf, place the black test lead of the voltmeter to the frame ground. Place the red test lead to the BAT2 (B-side battery connection) red cable. Verify it reads between -42 VDC and -57 VDC. Then place the red test lead of the voltmeter to the RET2 (B-side return ground) black cable and verify that no voltage is present.

Step 4 Return to your originating procedure (NTP).


DLP-B30 Install Ferrites on Power Cabling

Purpose

This task installs third-party ferrites on power cables to dampen electromagnetic interference (EMI) from the ONS 15327.

Tools/Equipment

Voltmeter

Block ferrite (Fair Rite 0443164151) for each pair of cables

Prerequisite Procedures

16 Connect the Office Ground to the ONS 15327

17 Connect Office Power to the ONS 15327 Shelf (Screw-Lock Power Connector)

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Note Ferrites must be added to meet the requirements of GR 1089. Refer to the ferrite manufacturer documentation for proper use and installation of the ferrites.



Step 1 Wrap the cables once around and through the block ferrites.

Step 2 Place the block ferrite within 5 to 6 inches of the power terminals.

Step 3 Return to your originating procedure (NTP).


NTP-B7 Install the Fan-Tray Assembly

Purpose

This procedure installs the fan-tray assembly.

Tools/Equipment

#2 Phillips screwdriver

Medium slot-head screwdriver

Small slot-head screwdriver

Prerequisite Procedures

2 Install the Shelf Assembly

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Caution Do not operate an ONS 15327 without a fan-tray air filter. A fan-tray air filter is mandatory.


Caution You must place the edge of the air filter flush against the front of the fan-tray assembly compartment when installing the fan-tray assembly on top of the air filter. Failure to do so could result in damage to the air filter, the fan-tray assembly, or both.


Caution Do not force a fan-tray assembly into place. Doing so can damage the connectors on the fan-tray assembly and/or the connectors on the back panel of the shelf assembly.


Step 1 If cables are installed, reposition them away from the fan-tray assembly slot.

Step 2 Slide the fan-tray assembly into the shelf assembly until the electrical plug at the rear of the tray plugs into the corresponding receptacle on the backplane.

Step 3 Secure the fan-tray assembly into the slot using the attached fastening screw.

Step 4 After power is supplied, confirm that the FAN STATUS LED on the front of the fan-tray assembly is illuminated. This indicates that the fan-tray assembly is operating.

The FAN STATUS LED illuminates only when an XTC card is installed.

Figure 1-8 shows the location of the fan-tray assembly.

Figure 1-8 Installing the Fan-Tray Assembly

Step 5 Continue with the "217 Install the XTCs" procedure.

Stop. You have completed this procedure.


NTP-B217 Install the XTCs

Purpose

This procedure installs the Cross-Connect Timing and Control (XTC) cards in Slots 5 and 6.

Tools/Equipment

None

Prerequisite Procedures

7 Install the Fan-Tray Assembly

216 Install the Mechanical Interface Cards

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

Retrieve or higher



Warning During this procedure, wear grounding wrist straps to avoid ESD damage to the card. Do not directly touch the backplane with your hand or any metal tool to avoid the risk of shock.



Note Because all traffic cards boot from the working XTC card, at least one XTC card must be installed in order to boot any traffic cards.



Step 1 Install an XTC card in Slot 6 ( Figure 1-9):

a. Open the card ejectors.

b. Slide the card along the guide rails into the slot.

c. Close the ejectors.

d. Lock the cards into place by tightening the ejector locking screws.

Slot 6 is the working XTC card slot.

Step 2 Verify that the red FAIL LED blinks for approximately 30 seconds.


Note Older versions of the XTC card may have an amber FAIL LED.


Step 3 Verify that all LEDs blink once and turn off.

Step 4 After approximately 5 minutes, verify the ACT/STBY LED is green (active).

Step 5 Install the second XTC card in Slot 5.

Slot 5 is the protect XTC slot.

Step 6 After the LED boot sequence (Steps 3 and 4), verify that the ACT/STBY LED is amber. The amber LED indicates that the second XTC card is the standby XTC.

Step 7 Press the LAMP TEST button on the faceplate of each XTC and verify that all LEDs illuminate while you press the button.

Step 8 When you log into CTC, verify that the card appears in the correct slot on the node view screen and that the card is white on the CTC node view screen.

Figure 1-9 Installing an XTC (XTC 28-3)

Step 9 Continue with the "218 Install the Optical and Ethernet Cards" procedure.

Stop. You have completed this procedure.


NTP-B218 Install the Optical and Ethernet Cards

Purpose

This procedure installs the optical cards (OC-3, OC-12, and OC-48) and Ethernet cards (E10/100-4, G1000-2) in Slots 1 through 4.

Tools/Equipment

None

Prerequisite Procedures

7 Install the Fan-Tray Assembly

217 Install the XTCs

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

Retrieve or higher



Warning Install blank faceplates into empty card slots. Blank faceplates serve three functions: They prevent exposure to hazardous voltages and currents inside the ONS 15327 chassis, they eliminate electromagnetic interference (EMI) that might disrupt other equipment, and they direct the flow of cooling air through the chassis. Do not operate the system unless all cards and faceplates are in place.



Step 1 Install an Ethernet or optical card in Slots 1, 2, 3, or 4 ( Figure 1-10):

a. Open the card ejectors.

b. Slide the card along the guide rails into the slot.

c. Close the ejectors.

d. Lock the cards into place by tightening the ejector locking screws.

Step 2 Verify that the red FAIL LED illuminates for 20 to 30 seconds.

Step 3 Verify that the red FAIL LED blinks for 30 to 45 seconds.

Step 4 Verify that all LEDs blink once and turn off for 5 to 10 seconds.

Step 5 Verify the ACT LED illuminates.

Step 6 When you log into CTC, verify that the card appears in the correct slot on the CTC node view screen and appears white in node view.

Figure 1-10 Installing an Ethernet Card (E10/100-T)

Step 7 Repeat Steps 1 and 6 for each optical and Ethernet card you want to install.

Step 8 If you installed the G1000-2 card, complete the "DLP-D4 Install SFP Connectors on G1000-2 Cards" task.


Note If you need to remove an SFP, complete the "DLP-D6 Remove SFP Connectors from G1000-2 Cards" task.


Stop. You have completed this procedure.


DLP-D4 Install SFP Connectors on G1000-2 Cards

Purpose

This task installs small form-factor pluggables (SFPs) and attaches the fiber.

Tools/Equipment

Short wavelength (1000BaseSX): 15327-SFP-LC-SX

Long wavelength/long haul (1000BaseLX): 15327-SFP-LC-LX

Prerequisite Procedures

218 Install the Optical and Ethernet Cards

Required/As Needed

Required if you are G1000-2 cards.

Onsite/Remote

Onsite

Security Level

None



Note SFPs are hot-swappable and can be installed or removed while the card or shelf assembly is powered and running.



Warning Invisible laser radiation may be emitted from the aperture ports of the single-mode fiber optic modules when no cable is connected. Avoid exposure and do not stare into open apertures.



Step 1 Remove the SFP from its protective packaging.

Step 2 Check the label to verify that the SFP is the correct type (SX or LX) for your network.

Step 3 Verify that you are installing compatible SFPs; for example, SX to SX, LX to LX. SFPs must be matched on either end by type.

Step 4 Plug the duplex connector of the fiber into a Cisco-supported SFP connector. If the new SFP connector has a latch, close the latch over the cable to secure it.

Step 5 Plug the cabled SFP connector into the G1000-2 card port until it clicks.

Step 6 Return to your originating procedure (NTP).


DLP-D6 Remove SFP Connectors from G1000-2 Cards

Purpose

This task removes SFPs from your Ethernet cards.

Tools/Equipment

None

Prerequisite Procedures

4 Install SFP Connectors on G1000-2 Cards

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Step 1 Disconnect the network fiber cable from the SFP duplex connector. If the SFP connector has a latch securing the fiber cable, pull it upward to release the cable.


Warning Invisible laser radiation may be emitted from disconnected fibers or connectors. Do not stare into beams or view directly with optical instruments.


Step 2 Pull the fiber cable straight out of the connector.

Step 3 Unplug the SFP connector and fiber from the G1000-2 card.

Step 4 Slide the SFP out of the Gigabit Ethernet card slot.

Step 5 Return to your originating procedure (NTP).


NTP-B219 Remove and Replace a Card

Purpose

This procedure describes how to remove and replace cards in the ONS 15327 shelf.

Tools/Equipment

None

Prerequisite Procedures

None

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

Provisioning or higher



Step 1 If you are not logged into CTC and you need to remove a card, remove the card as described in Step 3. When you log into CTC, troubleshoot the mismatched equipment (MEA) alarm with the Cisco ONS 15327 Troubleshooting Guide.

Step 2 If you are logged into CTC, either:

Complete the "DLP-B320 Delete a Card" task and continue with Step 3 or

Complete the "DLP-B247 Change an Optical Card" task to delete a card and replace it with a different optical card while maintaining existing provisioning.

Step 3 Physically remove the card:

a. Open the card latches/ejectors.

b. Use the latches/ejectors to pull the card forward and away from the shelf.

Step 4 Insert the new card using one of the following procedures as applicable:

217 Install the XTCs

218 Install the Optical and Ethernet Cards

Stop. You have completed this procedure.


DLP-B320 Delete a Card

Purpose

This task deletes a card from CTC.

Tools/Equipment

None

Prerequisite Procedures

60 Log into CTC

Required/As Needed

As needed

Onsite/Remote

Both

Security Level

Provisioning or higher



Step 1 On the shelf graphic, right-click the card that you want to remove and choose Delete Card.

You cannot delete a card if any of the following conditions apply:

The card is one of two installed XTC cards (a default XTC protection group was created); to replace an XTC card, refer to the Replace Hardware chapter in the Cisco ONS 15454 Troubleshooting Guide

The card is part of a protection group; see 155 Delete a Protection Group

The card has circuits; see 152 Delete Circuits

The card is part of a bidirectional line switched ring (BLSR); see 213 Remove a BLSR Node

The card is being used for timing; see 157 Change the Node Timing Source

The card has a SONET DCC termination; see
204 Delete a SONET DCC Termination


Note If you do not remove a card from the shelf after you delete it in CTC, it will reboot and reappear in CTC.


Step 2 Return to your originating procedure (NTP).


DLP-B247 Change an Optical Card

Purpose

This task describes how to change an optical card while maintaining existing provisioning, including DCCs, circuits, protection, timing, and rings. You cannot change a multiport card to a card with a smaller number of ports, and you cannot change a card to an identical type of card.

Tools/Equipment

None

Prerequisite Procedures

60 Log into CTC

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

Provisioning or higher



Caution Physically removing an optical card can cause a loss of working traffic or a protection switch. See Chapter 11, "Upgrade Cards and Spans" for information on upgrading traffic to a higher speed.


Step 1 If the card the active card in a 1+1 protection group, switch traffic away from the card:

a. Log into a node on the network. If you are already logged in, go to Step b.

b. Display the CTC node (login) view.

c. Click the Maintenance > Protection tabs.

d. Double-click the protection group that contains the reporting card.

e. Click the active card of the selected group.

f. Click Switch and Yes in the Confirmation dialog box.

Step 2 In node view, right-click the card that you want to remove and choose Change Card.

Step 3 From the Change Card drop-down menu, choose the desired card type and click OK. A Mismatched Equipment Alarm (MEA) will appear until you replace the card.

Step 4 Physically remove the card:

a. Open the card latches/ejectors.

b. Use the latches/ejectors to pull the card forward and away from the shelf.

Step 5 Return to your originating procedure (NTP).


NTP-B115 Preprovision a Slot

Purpose

This procedure describes how to preprovision a slot in the software before physical card installation.

Tools/Equipment

None

Prerequisite Procedures

"Connect the PC and Log into the GUI"

Required/As Needed

As needed

Onsite/Remote

Onsite or Remote

Security Level

Provisioning or higher



Step 1 Log into the ONS 15454. See the "DLP-B60 Log into CTC" task for instructions. The node (default) view displays. If you are already logged in, continue with Step 2.

Step 2 Right-click the empty slot where you will later install a card.

Step 3 From the Add Card popup menu, choose the card type that will be installed.


Note When you preprovision a slot, the card appears purple in the CTC shelf display, rather than white when a card is physically in the slot.


Step 4 Continue with the "221 Install Optical Cables" procedure.

Stop. You have completed this procedure.


NTP-B8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

Purpose

This procedure describes how to install alarm, timing, LAN, and craft wires.

Tools/Equipment

Alarm cable, CAT-5 terminated with RJ-45 for all alarm connections

#22 or #24 shielded AWG wire

Prerequisite Procedures

2 Install the Shelf Assembly

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Step 1 Complete the "DLP-B321 Install External Alarm Cables" task as necessary.

Step 2 Complete the "DLP-B322 Install Timing Cables" task as needed. Timing wires are necessary to provision external timing.

Step 3 Complete the "DLP-B323 Install the Serial Cable for TL1 Craft Interface" task as needed. Craft wires are required to access TL1 using the craft interface.

Step 4 Complete the "DLP-B324 Install DS-1 Champ Cables on a MIC" task as needed to carry DS-1 traffic.

Step 5 Complete the "DLP-B325 Install Coaxial Cable With BNC Connectors" task as needed to carry DS-3 traffic.


Caution Always use the supplied ESD wristband when working with a powered ONS 15327. Plug the wristband cable into the ESD jack located between the top high-speed and XTC slots.

Step 6 Continue with the "220 Install the Electrical Cables" procedure.

Stop. You have completed this procedure.


DLP-B321 Install External Alarm Cables

Purpose

This task installs alarm cables on the MICs so that you can provision external (environmental) alarms and controls.

Tools/Equipment

Alarm cable, CAT-5 terminated with RJ-45 for all alarm connections

Prerequisite Procedures

2 Install the Shelf Assembly

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Step 1 Plug one end of the alarm cable into the ALARM port on the MIC.

Step 2 Plug the other end of the cable into the alarm-collection equipment according to local site practice.

Step 3 Repeat Steps 1 and 2 for the other MIC.


Note You can use the alarm cutoff (ACO) button to extinguish audible alarms.


Step 4 To define the six external alarm inputs and two external alarm outputs using CTC, see the "32 Provision External Alarms and Controls on the XTC" procedure. Table 1-1 shows the input alarm pinouts and the corresponding alarm numbers assigned to each MIC/port. Table 1-2 shows the output alarm pinouts. Refer to these tables when connecting alarm cables to the ONS 15327. See Figure 1-11 for RJ-45 pin numbering.

Table 1-1 Alarm Input Pin Assignments 

Alarm Number (MIC A)
Alarm Number (MIC B)
RJ-45 Pin Number
Function


2


1

5

Alarm 2+

6

Alarm 2-


4


3

3

Alarm 1+

4

Alarm 1-


6


5

1

Alarm 0+

2

Alarm 0-


Table 1-2 Alarm (External Control) Output Pin Assignments

Alarm Number (MIC A)
Alarm Number (MIC B)
RJ-45 Pin Number
Function


2


1

7

Contact+

8

Contact-


Figure 1-11 Pins 1 and 8 on the RJ-45 Connector

Step 5 Return to your originating procedure (NTP).


DLP-B322 Install Timing Cables

Purpose

This task installs timing cables on the MICs so that you can provide BITS timing to the ONS 15327.

Tools/Equipment

100-ohm shielded BITS clock cable pair #22 or #24 AWG (0.51 mmІ or 0.64 mmІ), twisted-pair T1-type

Prerequisite Procedures

2 Install the Shelf Assembly

Required/As Needed

Required if the node is using external BITS timing

Onsite/Remote

Onsite

Security Level

None



Step 1 Plug one end of the timing cable into the BITS port on the MIC.

Step 2 Plug the other end of the cable into the BITS clock according to local site practice.

Step 3 Repeat Steps 1 and 2 for the other MIC. See Table 1-3, Figure 1-12, and Figure 1-13 when connecting BITS cables to the ONS 15327.

Table 1-3 BITS Cable Pin Assignments 

MIC A
MIC B
RJ-45 Pin Number
Function


BITS 1 In


BITS 2 In

3

BITS Input+

4

BITS Input-


BITS 1 Out


BITS 2 Out

7

BITS Output+

8

BITS Output-


Figure 1-12 BITS In Pins on the RJ-45 Connector

Figure 1-13 BITS Out Pins on the RJ-45 Connector

Table 1-4 External Timing Pin Assignments for BITS 

External Device
Contact
Tip & Ring
Function

First external device

A3 (BITS 1 Out)

Primary ring (-)

Output to external device

B3 (BITS 1 Out)

Primary tip (+)

Output to external device

A4 (BITS 1 In)

Secondary ring (-)

Input from external device

B4 (BITS 1 In)

Secondary tip (+)

Input from external device

Second external device

A1 (BITS 2 Out)

Primary ring (-)

Output to external device

B1 (BITS 2 Out)

Primary tip (+)

Output to external device

A2 (BITS 2 In)

Secondary ring (-)

Input from external device

B2 (BITS 2 In

Secondary tip (+)

Input from external device



Note For more detailed information about timing, refer to the Cisco ONS 15327 Reference Manual. To set up system timing, see the "28 Set Up Timing" procedure.


Step 4 Return to your originating procedure (NTP).


DLP-B323 Install the Serial Cable for TL1 Craft Interface

Purpose

This task installs the TL1 craft interface.

Tools/Equipment

Serial cable (DB-9)

Prerequisite Procedures

2 Install the Shelf Assembly

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Step 1 Plug one end of the serial cable into the front of the XTC card.

Step 2 Connect the other end to the PC you want to use to access the craft.


Note You can connect to either the active or standby XTC DB-9 plug to gain terminal access, but not both simultaneously.


Step 3 Return to your originating procedure (NTP).


NTP-B220 Install the Electrical Cables

Purpose

This procedure describes how to install the electrical DS-1 (AMP Champ) and DS-3 (coaxial) cables. To carry electrical traffic on the ONS 15327, you must install electrical cable.

Tools/Equipment

Shielded coaxial cable terminated with BNC connectors for DS-3 ports

Shielded ABAM cable terminated with Champ connectors for DS-1 ports with #22 or #24 AWG ground wire (typically about two feet in length)

Prerequisite Procedures

8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Caution Always use the supplied ESD wristband when working with a powered ONS 15327. Plug the wristband cable into the ESD jack located between the top traffic and XTC slots.


Step 1 Complete the "DLP-B324 Install DS-1 Champ Cables on a MIC" task as needed.

Step 2 Complete the "DLP-B325 Install Coaxial Cable With BNC Connectors" task as needed.

Step 3 Complete the "DLP-B326 Route Electrical Cables" task as needed.

Step 4 Continue with the "221 Install Optical Cables" procedure.

Stop. You have completed this procedure.


DLP-B324 Install DS-1 Champ Cables on a MIC

Purpose

This task installs DS-1 cables.

Tools/Equipment

One of the following DS-1 cables (either right-angle or straight):

Right-angle DS-1 cable

Amphenol GCA70 03006 RSE (30 feet)

Amphenol GCA70 03007 RSE (50 feet)

Amphenol GCA70 03008 RSE (100 feet)

Amphenol GCA70 03009 RSE (250 feet)

Volex VLX979-30 (30 feet)

Volex VLX979-50 (50 feet)

Volex VLX979-100 (100 feet)

Volex VLX979-250 (250 feet)

Straight DS-1 cable

Installing Champ connector DS-1 cables requires 64-pin bundled cable connectors with a 64-pin male Champ connector. You need Champ connector #552285-1 for the plug side and #1-552496-1 for the right-angle shell housing, or their functional equivalents.

Prerequisite Procedures

8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Caution Always use the supplied ESD wristband when working with a powered ONS 15327. Plug the wristband cable into the ESD jack located between the top high-speed and XTC slots.


Step 1 Prepare a 56-wire cable for each DS-1 connection you will make. See Table 1-5 for the ONS 15327 Champ connector pin assignments.

Table 1-5 Pin Assignments for Champ Connector (the shaded area corresponds to the white/orange binder group) 

Signal/Wire
Pin
Pin
Signal/Wire
Signal/Wire
Pin
Pin
Signal/Wire

Tx Tip 1
white/blue

1

33

Tx Ring 1
blue/white

Rx Tip 1
yellow/orange

17

49

Rx Ring 1
orange/yellow

Tx Tip 2 white/orange

2

34

Tx Ring 2
orange/white

Rx Tip 2
yellow/green

18

50

Rx Ring 2
green/yellow

Tx Tip 3
white/green

3

35

Tx Ring 3
green/white

Rx Tip 3
yellow/brown

19

51

Rx Ring 3
brown/yellow

Tx Tip 4
white/brown

4

36

Tx Ring 4
brown/white

Rx Tip 4
yellow/slate

20

52

Rx Ring 4
slate/yellow

Tx Tip 5
white/slate

5

37

Tx Ring 5
slate/white

Rx Tip 5
violet/blue

21

53

Rx Ring 5
blue/violet

Tx Tip 6
red/blue

6

38

Tx Ring 6
blue/red

Rx Tip 6
violet/orange

22

54

Rx Ring 6
orange/violet

Tx Tip 7
red/orange

7

39

Tx Ring 7
orange/red

Rx Tip 7
violet/green

23

55

Rx Ring 7
green/violet

Tx Tip 8
red/green

8

40

Tx Ring 8
green/red

Rx Tip 8
violet/brown

24

56

Rx Ring 8
brown/violet

Tx Tip 9
red/brown

9

41

Tx Ring 9
brown/red

Rx Tip 9
violet/slate

25

57

Rx Ring 9
slate/violet

Tx Tip 10
red/slate

10

42

Tx Ring 10
slate/red

Rx Tip 10
white/blue

26

58

Rx Ring 10
blue/white

Tx Tip 11
black/blue

11

43

Tx Ring 11
blue/black

Rx Tip 11
white/orange

27

59

Rx Ring 11
orange/white

Tx Tip 12
black/orange

12

44

Tx Ring 12
orange/black

Rx Tip 12
white/green

28

60

Rx Ring 12
green/white

Tx Tip 13
black/green

13

45

Tx Ring 13
green/black

Rx Tip 13
white/brown

29

61

Rx Ring 13
brown/white

Tx Tip 14
black/brown

14

46

Tx Ring 14
brown/black

Rx Tip 14
white/slate

30

62

Rx Ring 14
slate/white

Tx Spare 0+ N/A

15

47

Tx Spare0- N/A

Rx Spare0+ N/A

31

63

Rx Spare 0- N/A

Tx Spare 1+ N/A

16

48

Tx Spare1- N/A

Rx Spare1+ N/A

32

64

Rx Spare 1- N/A


Step 2 Connect the male Champ connector on the cable to the female Champ connector on the ONS 15327 MIC.

The DS-1 cable can have a straight or right-angle configuration. Figure 1-14 shows a straight DS-1 cable.


Note To install the right-angle DS-1 cable, you must have the screw-lock power connector installed.


Figure 1-14 Straight DS-1 Cable

Figure 1-15 shows a right-angle DS-1 cable.

Figure 1-15 Right-Angle DS-1 Cable

Step 3 Use the screws on the male connector to secure the connection. Figure 1-16 shows a straight DS-1 cable installation.

Figure 1-16 Installing a Straight DS-1 Cable

Step 4 Return to your originating procedure (NTP).


DLP-B325 Install Coaxial Cable With BNC Connectors

Purpose

This task installs the coaxial cable with BNC connectors to connect DS-3 signals to the ONS 15327.

Tools/Equipment

Shielded coaxial cable terminated with BNC connectors for DS-3 ports

Prerequisite Procedures

None

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Caution Always use the supplied ESD wristband when working with a powered ONS 15327. Plug the wristband cable into the ESD jack located between the top high-speed and XTC slots.


Step 1 Place a BNC cable connector over the connector on the MIC.

Figure 1-17 shows how to connect a coaxial cable to an ONS 15327 MIC.

Figure 1-17 Installing a Coaxial Cable with BNC Connectors

Step 2 Position the cable connector so that the slot in the connector is above the corresponding notch on the MIC connection point.

Step 3 Gently push the connector down until the notch on the MIC connector slides into the slot on the cable connector.

Step 4 Turn the cable connector until the notch clicks into place.

Step 5 Return to your originating procedure (NTP).


DLP-B326 Route Electrical Cables

Purpose

Use this task to route and manage electrical cables.

Tools/Equipment

None

Prerequisite Procedures

220 Install the Electrical Cables

Required/As Needed

Required if using electrical cards

Onsite/Remote

Onsite

Security Level

None



Caution Because cables can be damaged or cut, Cisco recommends that you diversely route redundant cables along different paths. If you installed the tie-down bar, you can run one cable across the tie-down bar and secure it using tie-wraps or other site-specific methods. You should route the other cable in the opposite direction. You can also route the cable through the cable storage drawer. See the "NTP-B223 Install the Fiber-Optic Cable Storage Drawer" procedure on page D-2 and the "NTP-B224 Route Cables Through the Fiber-Optic Cable Storage Drawer" procedure on page D-2.


Step 1 Route the cables to the nearest side of the shelf assembly through the side cutouts according to local site practice.

Step 2 Label all cables at each end of the connection to avoid confusion with cables that are similar in appearance.

Step 3 Return to your originating procedure (NTP).


NTP-B221 Install Optical Cables

Purpose

This procedure describes how to install fiber-optic cables on optical cards and small form-factor pluggable (SFP) interfaces.

Tools/Equipment

Single-mode SC fiber jumpers with UPC polish (55 dB or better) for OC12 and OC-48 cards and fiber jumpers with LC connectors for the OC-3 card

Fiber boot

Prerequisite Procedures

218 Install the Optical and Ethernet Cards

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Warning Invisible laser radiation can be emitted from the aperture port when no cable is connected. To avoid exposure to laser radiation do not stare into open apertures.



Caution Always use the supplied electrostatic discharge wristband when working with a powered ONS 15327. Plug the wristband cable into the ESD jack located between the top high-speed and XTC slots.


Note You can install the fiber immediately after installing the cards, or wait until you are ready to turn up the network. See "Turn Up Network."



Note Inspect and clean all fiber connectors thoroughly. See the "NTP-B112 Clean Fiber Connectors" procedure on page 14-20 for instructions. Dust particles can degrade performance. Put caps on any fiber connectors that are not used.



Note To install fiber-optic cables in the ONS 15327, a fiber cable with the corresponding connector type must be connected to the transmit and receive ports on the ONS 15327 cards.



Step 1 Test the optical receive levels for the installed cards and attenuate them accordingly. See Table 1-6 for the minimum and maximum levels.

Table 1-6 Optical Transmit and Receive Levels 

Card
Transmit
Receive
Minimum
Maximum
Minimum
Maximum

OC3 IR 4 1310

-15 dBm

-8 dBm

-28 dBm

-8 dBm

OC12 IR 1310

-15 dBm

-8 dBm

-29 dBm

-7 dBm

OC12 LR 1550

-3 dBm

+2 dBm

-29 dBm

-7 dBm

OC48 IR 1310

-5 dBm

0 dBm

-18 dBm

-0 dBm

OC48 LR 1310

-2 dBm

+3 dBm

-28 dBm

-8 dBm


Step 2 As needed, complete the "DLP-B327 Install Fiber-Optic Cables on the LGX Interface" task. Figure 1-18 shows the cable location.

Step 3 As needed, complete the "DLP-B42 Install Fiber-Optic Cables on OC-N Cards" task.

Step 4 As needed, complete the "DLP-B43 Install Fiber-Optic Cables for UPSR Configurations" task.

Step 5 As needed, complete the "DLP-B44 Install Fiber-Optic Cables for BLSR Configurations" task.

Figure 1-18 Installing a Fiber-Optic Cable

Step 6 As needed, complete the "DLP-B46 Route Fiber-Optic Cables" task.

Step 7 Continue with the "NTP-B13 Perform the Shelf Installation Acceptance Test" task.

Stop. You have completed this procedure.


DLP-B327 Install Fiber-Optic Cables on the LGX Interface

Purpose

This task installs fiber-optic cables on the Lightguide Cross Connect (LGX) interface in the Central Office.

Tools/Equipment

Fiber-optic cables

Prerequisite Procedures

218 Install the Optical and Ethernet Cards

NTP-B112 Clean Fiber Connectors, page 14-20

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Note Inspect and clean all fiber connectors thoroughly. See the "NTP-B112 Clean Fiber Connectors" procedure on page 14-20 for instructions. Dust particles can degrade performance. Put caps on any fiber connectors that are not used.



Step 1 Align the keyed ridge of the cable connector with the receiving SC connector on the LGX faceplate connection point. Each module supports at least one transmit and one receive connector to create an optical carrier port.

Step 2 Gently insert the cable connector into the faceplate connection point until the connector snaps into place.

Step 3 Connect the fiber optic cable to the OC-N card. See the "DLP-B42 Install Fiber-Optic Cables on OC-N Cards" task.

Step 4 Return to your originating procedure (NTP).


DLP-B42 Install Fiber-Optic Cables on OC-N Cards

Purpose

This task installs fiber-optic cables on optical (OC-N) cards.

Tools/Equipment

Fiber-optic cables

Prerequisite Procedures

218 Install the Optical and Ethernet Cards

NTP-B112 Clean Fiber Connectors, page 14-20

327 Install Fiber-Optic Cables on the LGX Interface (as applicable)

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Note Inspect and clean all fiber connectors thoroughly. See the "NTP-B112 Clean Fiber Connectors" procedure on page 14-20 for instructions. Dust particles can degrade performance. Put caps on any fiber connectors that are not used.



Note ONS 15327 OC-12 and OC-48 cards have SC connectors and the OC-3 and G1000-2 cards have LC connectors. On ONS 15327 OC-12 and OC-48 card ports, the left connector is the transmit port and the right connector is the receive port.



Step 1 Align the keyed ridge of the cable connector with the receiving connector on the faceplate connection point. Each card supports at least one transmit and one receive connector to create an optical carrier port.

Step 2 Gently insert the cable connector into the faceplate connection point until the connector snaps into place.

Step 3 Return to your originating procedure (NTP).


DLP-B43 Install Fiber-Optic Cables for UPSR Configurations

Purpose

This task installs the fiber-optic cables to the east and west UPSR ports at each node. See "Turn Up Network" to provision and test UPSR configurations.

Tools/Equipment

Fiber-optic cables

Prerequisite Procedures

218 Install the Optical and Ethernet Cards

NTP-B112 Clean Fiber Connectors, page 14-20

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Note To avoid error, connect fiber-optic cable so that the highest slot in the shelf represents the east port, and the lowest slot represents the west port. Fiber connected to an east port at one node must plug into the west port on an adjacent node.



Note Inspect and clean all fiber connectors thoroughly. See the "NTP-B112 Clean Fiber Connectors" procedure on page 14-20 for instructions. Dust particles can degrade performance. Put caps on any fiber connectors that are not used.



Note You can install the fiber immediately after installing the cards, or wait until you are ready to turn up the network. See "Turn Up Network."



Step 1 Plan your fiber connections. Use the same plan for all UPSR nodes.

Step 2 Plug the fiber into the transmit (Tx) connector of an OC-N card at one node and plug the other end of the fiber into the receive (Rx) connector of an OC-N card at the adjacent node. The card will display a signal fail (SF) LED if the transmit and receive fibers are mismatched (for example, one fiber connects a receive port on one card to a receive port on another card).

Step 3 Repeat Step 2 until you have configured the entire ring.

Figure 1-19 shows fiber connections for a four-node UPSR with trunk (span) cards in Slot 5 (west) and Slot 12 (east).

Figure 1-19 Connecting Fiber to a Four-Node UPSR

If you are creating a UPSR dual ring interconnect, Figure 1-20 shows a traditional dual ring interconnect example.

Figure 1-20 Connecting Fiber to an Eight-Node Traditional UPSR Dual-Ring Interconnect

Step 4 Return to your originating procedure (NTP).


DLP-B44 Install Fiber-Optic Cables for BLSR Configurations

Purpose

This task installs the fiber-optics to the east and west BLSR ports at each node. See "Turn Up Network" to provision and test BLSR configurations.

Tools/Equipment

Fiber-optic cables

Prerequisite Procedures

218 Install the Optical and Ethernet Cards

NTP-B112 Clean Fiber Connectors, page 14-20

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Note To avoid error, connect fiber-optic cable so that the highest slot on the 15327 chassis represents the east port, and the lowest slot represents the west port. Fiber connected to an east port at one node must plug into the west port on an adjacent node.



Note Inspect and clean all fiber connectors thoroughly. See the "NTP-B112 Clean Fiber Connectors" procedure on page 14-20 for instructions. Dust particles can degrade performance. Put caps on any fiber connectors that are not used.



Note You can install the fiber immediately after installing the cards, or wait until you are ready to turn up the network. See "Turn Up Network."



Step 1 Plan your fiber connections. Use the same plan for all BLSR nodes.

Step 2 Plug the fiber into the transmit (Tx) connector of an OC-N card at one node and plug the other end into the receive (Rx) connector of an OC-N card at the adjacent node. The card will display a signal fail (SF) LED if the transmit and receive fibers are mismatched.

Step 3 Repeat Step 2 until you have configured the entire ring.

Figure 1-21 shows fiber connections for a BLSR with trunk (span) cards in Slot 5 (west) and Slot 12 (east).

Figure 1-21 Connecting Fiber to a Four-Node, Two-Fiber BLSR

Step 4 Return to your originating procedure (NTP).


DLP-B46 Route Fiber-Optic Cables

Purpose

This task describes how to route fiber-optic cables through the cable guides on the sides of the shelf assembly.

Tools/Equipment

None

Prerequisite Procedures

221 Install Optical Cables

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

None



Caution Because an optical cable can be damaged or cut, Cisco recommends that you diversely route redundant cables along different paths. If you installed the tie-down bar, you can run one cable across the tie-down bar and secure it using tie-wraps or other site-specific methods. You should route the other cable in the opposite direction. You can also route the cable through the cable storage drawer. See the "NTP-B223 Install the Fiber-Optic Cable Storage Drawer" procedure on page D-2 and the "NTP-B224 Route Cables Through the Fiber-Optic Cable Storage Drawer" procedure on page D-2.


Step 1 Locate the cable guides on either side of the shelf assembly.

Step 2 Gently route the fiber cables through the cable guides.

Step 3 Return to your originating procedure (NTP).


NTP-B13 Perform the Shelf Installation Acceptance Test

Purpose

Use this procedure to perform a shelf installation acceptance test.

Tools/Equipment

Voltmeter

Prerequisite Procedures

"Install Hardware"

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

Retrieve or higher



Step 1 Complete Table 1-7 by verifying that each procedure was completed.

Table 1-7 ONS 15327 Shelf Installation Task Summary 

Description
Completed

1 Unpack and Inspect the ONS 15327 Shelf Assembly

 

2 Install the Shelf Assembly

 

216 Install the Mechanical Interface Cards

 

6 Install the Power and Ground

 

7 Install the Fan-Tray Assembly

 

217 Install the XTCs

 

218 Install the Optical and Ethernet Cards

 

8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

 

220 Install the Electrical Cables

 

221 Install Optical Cables

 

Step 2 Check each wire and cable connection to make sure all cables are locked securely. If a wire or cable is loose, return to the appropriate procedure in this chapter to correct it.

Step 3 Complete the "DLP-B33 Measure Voltage" task.

Stop. You have completed this procedure.


DLP-B33 Measure Voltage

Purpose

This task measures power so you can verify correct power and returns.

Tools/Equipment

Voltmeter

Prerequisite Procedures

6 Install the Power and Ground

Table 1-7.

Required/As Needed

Required

Onsite/Remote

Onsite

Security Level

None



Step 1 Using a voltmeter, verify the office ground and power shows the power terminals):

a. Place the black lead (positive) on the frame ground on the rack. Hold it there while completing
Step b.

b. Place the red lead (negative) on the fuse power points and alarm panel to verify that they read between -42 VDC and -57 VDC (power) and 0 (return ground).

Step 2 Using a voltmeter, verify the shelf ground and power wiring:

a. Place the black lead (positive) on the RET1 and the red lead on the BAT1 point. Verify a reading between -42 VDC and -57 VDC. If there is no voltage, check the following:

Battery and ground reversed to the shelf

Battery is open or missing

Return is open or missing

b. Repeat Step 2 for the RET2 and BAT2 if the B power feed is provided.

Step 3 Return to your originating procedure (NTP).



hometocprevnextglossaryfeedbacksearchhelp

Posted: Mon Feb 25 06:11:52 PST 2008
All contents are Copyright © 1992--2008 Cisco Systems, Inc. All rights reserved.
Important Notices and Privacy Statement.