cc/td/doc/product/ong/15400/r70docs
hometocprevnextglossaryfeedbacksearchhelp
PDF

Table Of Contents

Add and Remove Cards and Nodes

Before You Begin

NTP-G107 Permanently Remove or Remove and Replace DWDM Cards

DLP-G254 Place OPT-BST, OPT-BST-E, OPT-BST-L, and OPT-PRE Ports Out of Service

DLP-G318 Place OPT-BST, OPT-BST-E, OPT-BST-L, and OPT-PRE Ports In Service

NTP-G127 Add an AD-xC-xx.x Card to an OADM Node

NTP-G129 Add a DWDM Node

NTP-G130 Remove a DWDM Node

NTP-G146 Add a Rack and/or Shelf to a Multishelf Node

NTP-G147 Delete a Shelf and/or Rack from a Multishelf Node


Add and Remove Cards and Nodes


This chapter provides procedures for adding and removing dense wavelength division multiplexing (DWDM) cards and nodes.


Note Unless otherwise specified, "ONS 15454" refers to both ANSI and ETSI shelf assemblies.


Before You Begin

Before performing any of the following procedures, investigate all alarms and clear any trouble conditions. Refer to the Cisco ONS 15454 DWDM Troubleshooting Guide as necessary for general troubleshooting information and alarm or error descriptions.

This section lists the chapter procedures (NTPs). Turn to a procedure to view its tasks (DLPs).

1. G107 Permanently Remove or Remove and Replace DWDM Cards—Complete as needed.

2. G127 Add an AD-xC-xx.x Card to an OADM Node—Complete as needed.

3. G129 Add a DWDM Node—Complete as needed.

4. G130 Remove a DWDM Node—Complete as needed.

5. G146 Add a Rack and/or Shelf to a Multishelf Node—Complete as needed.

6. G147 Delete a Shelf and/or Rack from a Multishelf Node—Complete as needed.

NTP-G107 Permanently Remove or Remove and Replace DWDM Cards

Purpose

This procedure permanently removes or removes and replaces DWDM cards installed in the ONS 15454 shelf and rack.

Tools/Equipment

None

Prerequisite Procedures

NTP-G30 Install the DWDM Cards, page 3-46

NTP-G32 Install the Transponder and Muxponder Cards, page 3-51

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

Provisioning or higher



Caution Removing and replacing cards can be traffic affecting.


Caution Do not use this procedure to replace a TCC2 or TCC2P card. To replace a TCC2/TCC2P card, refer to the Cisco ONS 15454 DWDM Troubleshooting Guide.


Step 1 Complete the "DLP-G46 Log into CTC" task.


Note If you cannot log into Cisco Transport Controller (CTC) and you need to remove a card, remove the card as described in Step 6. After you log into CTC, troubleshoot the mismatched equipment alarm (MEA) with the Cisco ONS 15454 DWDM Troubleshooting Guide.


Step 2 Click the Alarms tab.

a. Verify that the alarm filter is not on. See the "DLP-G128 Disable Alarm Filtering" task as necessary.

b. Verify that no unexplained alarms appear on the network. If alarms appear, investigate and resolve them before continuing. Refer to the Cisco ONS 15454 DWDM Troubleshooting Guide for procedures.

Step 3 If you are removing and replacing a card, go to Step 5.

Step 4 If you are permanently removing a card, go to Step 11.

Step 5 To remove and replace a card, complete the following tasks, as needed:

The circuits traversing through the card that needs to be replaced (for example, an amplifier) need to be protection switched. For instance, if the card you want to replace is an active transponder (TXP) or muxponder (MXP) in a Y-cable protection group, complete the "DLP-G179 Apply a Force Y-Cable or Splitter Protection Switch" task on page 10-38 to force traffic away from the TXP or MXP that you will remove. If the card you want to replace is the standby TXP or MXP in a Y-cable protection group, complete the "DLP-G182 Apply a Lockout" task on page 10-40 to prevent traffic from switching to the TXP or MXP that you will remove.

If the card is an OSCM or OSC-CSM that is used as a node timing reference, complete the "NTP-G112 Change the Node Timing Reference" procedure on page 13-17 to change the timing reference to a card that will not be removed.

If the card is an OSCM or OSC-CSM with an optical service channel (OSC) or generic communications channel (GCC) termination, complete the "NTP-G85 Modify or Delete OSC Terminations, GCC Terminations, and Provisionable Patchcords" procedure on page 10-42 to delete the termination and recreate it on a card that will not be removed.


Note If you delete a card in CTC but do not remove it from the shelf, it will reboot and reappear in CTC.


Step 6 Physically remove the card:

a. Disconnect any cables.

b. Open the card latches/ejectors.

c. Use the latches/ejectors to pull the card forward and away from the shelf.

Step 7 Insert the new card using one of the following procedures as applicable:

NTP-G30 Install the DWDM Cards, page 3-46

NTP-G32 Install the Transponder and Muxponder Cards, page 3-51

Step 8 Continue with the "NTP-G34 Install Fiber-Optic Cables on DWDM Cards and DCUs" procedure on page 3-57.

Step 9 Complete the following tasks or procedures, as needed:

If you switched a Y-cable protection group in Step 5, complete the "DLP-G180 Clear a Manual or Force Y-Cable or Splitter Protection Switch" task on page 10-39.

If you deleted circuits in Step 5, complete the "DLP-G105 Provision Optical Channel Network Connections" task on page 7-11.

If you switched the timing reference in Step 5, complete the "NTP-G112 Change the Node Timing Reference" procedure on page 13-17 to change the reference back to the new card.

If you deleted an OSC or GCC termination in Step 5, complete the "NTP-G38 Provision OSC Terminations" procedure on page 3-84 or the "DLP-G76 Provision GCC Terminations" task on page 7-22.

Step 10 Go to Step 13.

Step 11 To permanently remove a card, complete the following tasks:

Delete the circuits associated with the card being removed. Complete the "DLP-G106 Delete Optical Channel Network Connections" task on page 7-14, and the "DLP-G347 Delete Optical Channel Client Connections" task on page 7-8 as needed.

Physically remove the card:

Disconnect any cables.

Open the card latches/ejectors.

Use the latches/ejectors to pull the card forward and away from the shelf.

Step 12 If the card you are removing is an OSCM, OSC-CSM, DWDM Amplifier, or Filter card, complete the following tasks; otherwise, go to Step 13.

Reconfigure the circuits (OCHCC, OCHNC, Trails) as needed. Complete the "DLP-G105 Provision Optical Channel Network Connections" task on page 7-11, and the "DLP-G346 Provision Optical Channel Client Connections" task on page 7-4 as needed.

Reload ANS provisioning. Complete the "NTP-G143 Import the Cisco MetroPlanner NE Update Configuration File" task on page 3-39.

Relaunch ANS. Complete the "NTP-G37 Run Automatic Node Setup" task on page 3-83.

Step 13 Click the Alarms tab.

a. Verify that the alarm filter is not on. See the "DLP-G128 Disable Alarm Filtering" task as necessary.

b. Verify that no unexplained alarms appear on the network. If alarms appear, investigate and resolve them. Refer to the Cisco ONS 15454 DWDM Troubleshooting Guide for procedures.

Stop. You have completed this procedure.


DLP-G254 Place OPT-BST, OPT-BST-E, OPT-BST-L, and OPT-PRE Ports Out of Service

Purpose

This task places OPT-BST, OPT-BST-E, OPT-BST-L, and OPT-PRE card ports out of service in preparation for card removal.

Tools/Equipment

None

Prerequisite Procedures

G46 Log into CTC

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Step 1 On the shelf graphic in CTC, double-click the OPT-BST, OPT-BST-E, OPT-BST-L, or OPT-PRE card with the ports that you want to put out of service.

Step 2 Click the Provisioning > Optical Line > Parameters tabs.

Step 3 In the Admin State column for the card's ports, choose OOS,DSBLD (ANSI) or Locked,disabled (ETSI) for each port that does not have an OOS-MA,DSBLD or Locked-enabled,disabled service state.

Step 4 Click Apply.

Step 5 In the confirmation dialog box, click Yes.

Step 6 Click the Provisioning > Opt Apli Line > Parameters tabs.

Step 7 In the Admin State column for the card's ports, choose OOS,DSBLD or Locked,disabled (ETSI) for each port that does not have an OOS-MA,DSBLD or Locked,disabled service state.

Step 8 Click Apply.

Step 9 In the confirmation dialog box, click Yes.

Step 10 Return to your originating procedure (NTP).


DLP-G318 Place OPT-BST, OPT-BST-E, OPT-BST-L, and OPT-PRE Ports In Service

Purpose

This task places OPT-BST, OPT-BST-E, OPT-BST-L, and OPT-PRE card ports in service.

Tools/Equipment

None

Prerequisite Procedures

G46 Log into CTC

Required/As Needed

As needed

Onsite/Remote

Onsite or remote

Security Level

Provisioning or higher



Step 1 On the shelf graphic in CTC, double-click the OPT-BST, OPT-BST-E, OPT-BST-L, or OPT-PRE card with the ports that you want to put in service.

Step 2 Click the Provisioning > Optical Line > Parameters tabs.

Step 3 In the Admin State column for the card's ports, choose IS,AINS (ANSI) or Unlocked-automaticInService (ETSI) for Port 1 (COM-RX) of the OPT-PRE or Ports 2 (OSC-RX) and 3 (COM-TX) of the OPT-BST, OPT-BST-E, or OPT-BST-L cards.

Step 4 Click Apply.

Step 5 In the confirmation dialog box, click Yes.

Step 6 Return to your originating procedure (NTP).


NTP-G127 Add an AD-xC-xx.x Card to an OADM Node

Purpose

This procedure adds an AD-xC-xx.x card to an optical add/drop multiplexing (OADM) node.

Tools/Equipment

None

Prerequisite Procedures

Chapter 3, "Turn Up a Node"

A Cisco MetroPlanner OADM site plan recalculated for the new OADM card

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

Provisioning or higher



Note Do not begin this procedure until the Cisco MetroPlanner site plan has been recalculated with the new AD-xC-xx.x card added to the OADM node.



Note During this procedure, you will use TL1 commands to delete and recreate optical channel network connection (OCHNC) cross-connects. You might need to refer to the Cisco ONS SONET TL1 Command Guide or the Cisco ONS 15454 SDH TL1 Command Guide.



Caution This procedure will affect the service of unprotected circuits that pass through the OADM node.


Step 1 Complete the "DLP-G46 Log into CTC" task at a node on the OADM network.

Step 2 In node view (single-shelf mode) or multishelf view (multishelf mode), display the OADM node where you will add the card.

Step 3 Click the Circuits tab.

Step 4 Make a list of all OCHNCs and/or OCHCCs that are carried on the express path for both the east-to-west (E > W) and west-to-east (W > E) directions.

Step 5 For OCHNCs and/or OCHCCs identified in Step 4 that are routed on the active path of a splitter or Y-cable protection group, force the traffic to the protect path in the opposite side of the ring using the "DLP-G179 Apply a Force Y-Cable or Splitter Protection Switch" task on page 10-38.

Step 6 Click the Circuits tab.

Step 7 Complete the following steps for all OCHNCs and/or OCHCCs carried on the express path that were identified in Step 4:

a. Choose the OCHNC or OCHCC circuit(s) and click Edit. (To choose multiple circuits, press the Shift key while you click the circuits.)

b. In the Edit Circuit dialog box, click the State tab.

c. In the State field on the right, choose OOS,DSBLD (ANSI) or Locked,disabled (ETSI) from the drop-down list.

d. Click Apply.

e. Repeat Steps a through d for each OCHNC or OCHCC circuit.

Step 8 From the Tools menu, choose Open TL1 Connection.

Step 9 In the Select Node dialog box, choose the OADM node where you will add the AD-xC-xx.x card and click OK.

Step 10 In the TL1 dialog box, use the DLT-OCHNC command to delete the OCHNC cross-connects for the express path OCHNC and/or the relative OCH-TRAIL for the OCHCCs listed in Step 4, as follows:

DLT-OCHNC:[<TID>]:<SRC>,<DST>:<CTAG>:::[CKTID=<CKTID>],[CMDMDE=<CMDMDE>];

where:

<SRC> is the Source access identifier from the "CHANNEL" section. In 2-way wavelength connection sources both directions need to be indicated.

<DST> is the Destination access identifier from the "LINE" section. In 2-way wavelength connection sources both directions need to be indicated.

<CKTID> is the cross-connect ID. The default is Blank or None. String of ASCII characters. Maximum length is 48. If CKTID is empty or null the CKTID field will not be displayed.

<CMDMDE> is the command execution mode.

For additional information, including valid command values, refer to the Cisco ONS SONET TL1 Command Guide or the Cisco ONS 15454 SDH TL1 Command Guide.

Step 11 Click Close to close the TL1 dialog box.

Step 12 In node view (single-shelf mode) or multishelf view (multishelf mode), click the Provisioning > WDM-ANS > Internal Patchcords tabs.

Step 13 Highlight the two express connections that carry the deleted circuits passing through the node. (The express connections are the only ones connecting an EXP_TX port on the last west-side OADM card, W > E, with an EXP_RX port on the first east-side OADM card, W > E.)

Step 14 Click Delete.

Step 15 Remove the physical express cables between the EXP_TX and EXP_RX ports specified in Step 13.

Step 16 Insert the new AD-xC-xx.x card in the slot identified by your Cisco MetroPlanner site plan.

Step 17 Complete the "NTP-G34 Install Fiber-Optic Cables on DWDM Cards and DCUs" procedure on page 3-57 for the OADM node, following the new internal connections table generated by Cisco MetroPlanner.

Step 18 Complete the "NTP-G152 Create and Verify Internal Patchcords" procedure on page 3-81.

Step 19 Import the recalculated OADM site parameters. See the "NTP-G143 Import the Cisco MetroPlanner NE Update Configuration File" task on page 3-39.

Step 20 In node view (single-shelf mode) or multishelf view (multishelf mode), click the Provisioning > WDM-ANS > Port Status tabs.

Step 21 Click Launch ANS.

Step 22 From the Tools menu, choose Open TL1 Connection.

Step 23 In the Select Node dialog box, choose the OADM node and click OK.

Step 24 In the TL1 dialog box, use the ENT-OCHNC command to create the OCHNC or relative OCH-Trail of the OCHCC cross-connects that were deleted in Step 10, as follows:

ENT-OCHNC:[<TID>]:<SRC>,<DST>:<CTAG>::[<WCT>]:[CKTID=<CKTID>],
[CMDMDE=<CMDMDE>]:[<PST>[,<SST>]];

where:

<SRC> is the Source access identifier from the "CHANNEL" section. In 2-way wavelength connection sources both directions need to be indicated.

<DST> is the Destination access identifier from the "LINE" section. In 2-way wavelength connection sources both directions need to be indicated.

<WCT> Wavelength connection type, either 1WAY or 2WAY. The default is 1WAY.

<CKTID> is the cross-connect ID. The default is Blank or None. String of ASCII characters. Maximum length is 48. If CKTID is empty or null the CKTID field will not be displayed.

<CMDMDE> is the command execution mode.

<PST> is the primary state, either IS or OOS.

<SST> is the secondary state.

For additional information and a list of valid command values, see the Cisco ONS SONET TL1 Command Guide or the Cisco ONS 15454 SDH TL1 Command Guide.

Step 25 Click Close to close the TL1 dialog box.

Step 26 In node view (single-shelf mode) or multishelf view (multishelf mode), click the Circuits tab.

Step 27 Complete the following steps for all OCHNCs and/or OCHCCs set to OOS,DSBLD (ANSI) or Locked,disabled (ETSI) in Step 7:

a. Choose the OCHNC or OCHCC circuit(s) and click Edit. To choose multiple circuits, press the Shift key while you click the circuits.

b. In the Edit Circuit dialog box, click the State tab.

c. In the State field on the right, choose IS,AINS (ANSI) or Unlocked,automaticInService (ETSI) from the drop-down list.

d. Click Apply, and then click OK.

Step 28 Complete the "DLP-G180 Clear a Manual or Force Y-Cable or Splitter Protection Switch" task on page 10-39 for OCHNCs and/or OCHCCs that were switched to the opposite side of the ring as part of a splitter or Y-cable protection group to return the traffic to its condition before the card was added.

Stop. You have completed this procedure.


NTP-G129 Add a DWDM Node

Purpose

This procedure adds a DWDM node to an existing Multi-Service Transport Platform (MSTP) network.

Tools/Equipment

None

Prerequisite Procedures

Chapter 3, "Turn Up a Node"

A Cisco MetroPlanner network plan recalculated for the new node

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

Provisioning or higher



Note Do not begin this procedure until the Cisco MetroPlanner network plan has been updated and recalculated with the new DWDM node.



Note This procedures assumes all turn-up procedures provided in Chapter 3, "Turn Up a Node,"have been completed at the node that will be added. If this has not been completed, do not continue. Complete the turn up procedures at the new node before you complete this procedure.



Note During this procedure, you will use TL1 commands to delete and recreate OCHNC and OCHCC cross-connects. You might need to refer to the Cisco ONS SONET TL1 Command Guide or the Cisco ONS 15454 SDH TL1 Command Guide.



Caution To complete this procedure, a span will be disconnected where the new node is added. This will affect the service of any unprotected circuits that pass through that span.


Step 1 At the node that will be added, complete the "G51 Verify DWDM Node Turn-Up" procedure. If the node has not been turned up, do not continue. Complete procedures in Chapter 3, "Turn Up a Node," and Chapter 4, "Perform Node Acceptance Tests," then begin this procedure again.

Step 2 If the Cisco MetroPlanner network design has not been updated and recalculated for the new node and client services, update and recalculate it now, following the procedures in the Cisco MetroPlanner documentation.

Step 3 Identify the fiber spans that must be disconnected to insert the new node.

Step 4 Complete the "DLP-G46 Log into CTC" task at a DWDM node that is active on the network where you want to add the new DWDM node.

Step 5 In network view, click the Circuits tab.

Step 6 Identify the OCHCCs and/or OCHNCs that are carried on the fiber span express path that you identified in Step 3 in both the east-to-west and west-to-east directions.

Step 7 If the OCHCC and/or OCHNC circuit is on the active path and is protected by a splitter or Y-cable protection group, complete the "DLP-G179 Apply a Force Y-Cable or Splitter Protection Switch" task on page 10-38 to force traffic away from the span where the node will be added. If not, continue with Step 8.

Step 8 For each circuit identified in Step 6 that was not switched in Step 7 (unprotected circuits), complete the following steps:

a. In network view, select the OCHNC and/or OCHCC circuit and click Edit.

b. In the Edit Circuit dialog box, click the State tab.

c. In the State field on the right, choose OOS,DSBLD (ANSI) or Locked,disabled (ETSI) from the drop-down list.

d. Click Apply, then click OK.

Step 9 Remove the fibers from the cards at the adjacent nodes that will connect to the new node.

Step 10 Install the fibers from the adjacent nodes that will connect to the new node using the "NTP-G34 Install Fiber-Optic Cables on DWDM Cards and DCUs" procedure on page 3-57.

Step 11 Create cross-connects on the new node for all circuits identified in Step 6:

a. From the Tools menu, choose Open TL1 Connection.

b. In the Select Node dialog box, choose the new node and click OK.

c. In the TL1 dialog box, use the ENT-OCHNC command to create the OCHNC and/or OCHCC cross-connects for each unprotected pass-through circuit as follows:

ENT-OCHNC:[<TID>]:<SRC>,<DST>:<CTAG>::[<WCT>]:[CKTID=<CKTID>],
[CMDMDE=<CMDMDE>]:[<PST>[,<SST>]];

where:

<SRC> is the Source access identifier from the "CHANNEL" section. In 2-way wavelength connection sources both directions need to be indicated.

<DST> is the Destination access identifier from the "LINE" section. In 2-way wavelength connection sources both directions need to be indicated.

<WCT> Wavelength connection type, either 1WAY or 2WAY. The default is 1WAY.

<CKTID> is the cross-connect ID. The default is Blank or None. String of ASCII characters. Maximum length is 48. If CKTID is empty or null the CKTID field will not be displayed.

<CMDMDE> is the command execution mode.

<PST> is the primary state, either IS or OOS.

<SST> is the secondary state.

For additional information and a list of valid command values, see the Cisco ONS SONET TL1 Command Guide or the Cisco ONS 15454 SDH TL1 Command Guide.

d. Click Close to close the TL1 dialog box.

e. Repeat Step 8 to change the circuits placed in OOS,DSBLD (ANSI) or Locked,disabled (ETSI) back in service by choosing IS-AINS (ANSI) or Unlocked,automaticInService (ETSI) in the State drop-down list.

Step 12 Complete the "DLP-G180 Clear a Manual or Force Y-Cable or Splitter Protection Switch" task on page 10-39 for the circuits that were switched in Step 7 to return the traffic to its original paths.

Step 13 Complete the "DLP-G106 Delete Optical Channel Network Connections" task on page 7-14 for circuits identified in Step 6 that will not be part of the traffic matrix after the node is added.

Step 14 Divide the circuits that existed previously into two groups: those that will terminate in the new node and those that will pass through it.

Step 15 For circuits that will terminate in the new node, complete the "DLP-G106 Delete Optical Channel Network Connections" task on page 7-14 and then the "DLP-G105 Provision Optical Channel Network Connections" task on page 7-11.

Step 16 Complete the "DLP-G105 Provision Optical Channel Network Connections" task on page 7-11 to create new circuits.

Stop. You have completed this procedure.


NTP-G130 Remove a DWDM Node

Purpose

This procedure removes a node from a DWDM network.

Tools/Equipment

None

Prerequisite Procedures

Chapter 3, "Turn Up a Node"

A Cisco MetroPlanner network plan recalculated for the new node

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

Provisioning or higher



Note Do not begin this procedure until the Cisco MetroPlanner network plan has been updated and recalculated with the DWDM node removed.



Note During this procedure, you will use TL1 commands to delete and recreate OCHNC or OCHCC cross-connects. You might need to refer to the Cisco ONS SONET TL1 Command Guide or the Cisco ONS 15454 SDH TL1 Command Guide.



Caution This procedure will affect the service of unprotected circuits that pass through the span where the node will be removed.


Step 1 If the Cisco MetroPlanner network design has not been updated and recalculated with the node removed, update and recalculate the design now, following the procedures in the Cisco MetroPlanner documentation.

Step 2 Complete the "NTP-G21 Log into the GUI" task on page 2-25 at the DWDM target node.

Step 3 Click the Circuits tab.

Step 4 Identify the OCHNCs and/or OCHCCs that pass through or are added and dropped at the node that will be removed (that is, the target node), in both the Side B-to-Side A and Side A-to-Side B directions.

Step 5 Complete the "DLP-G347 Delete Optical Channel Client Connections" task on page 7-8 and/or the "DLP-G106 Delete Optical Channel Network Connections" task on page 7-14 to delete OCHCCs and/or OCHNCs identified in Step 4 that terminate (add/drop) on the target DWDM node.

Step 6 If OCHNC and/or OCHCC circuits pass through the target node on the active path and are protected by a splitter or Y-cable protection group, navigate to a node connected to the target node and complete the "DLP-G179 Apply a Force Y-Cable or Splitter Protection Switch" task on page 10-38 to force the traffic away from the node that will be deleted. Otherwise, continue with Step 7.

Step 7 Complete the following steps for each circuit identified in Step 4 that was not deleted in Step 5 or switched in Step 6:

a. Select the OCHNCs or OCHCCs and click Edit.

b. In the Edit Circuit dialog box, click the State tab.

c. In the State field, choose OOS,DSBLD (ANSI) or Locked,disabled (ETSI) from the drop-down list.

d. Click Apply, then click OK.

Step 8 Delete the cross-connects on the target node for each circuit placed in the OOS-DSBLD or Locked,disabled state in Step 7:

a. From the Tools menu, choose Open TL1 Connection.

b. In the Select Node dialog box, select the new node and click OK.

c. In the TL1 dialog box, use the DLT-OCHNC command to delete the OCHNC cross-connects for each unprotected pass-through circuit as follows:

DLT-OCHNC:[<TID>]:<SRC>,<DST>:<CTAG>:::[CKTID=<CKTID>], [CMDMDE=<CMDMDE>];

where:

<SRC> is the source access identifier from the Channel section in a two-way wavelength.

<DST> is the destination access identifier from the LINEWL section in a two-way wavelength.

<CKTID> is the cross-connect ID. The default is Blank or None. CKTD is a string of ASCII characters. The maximum length is 48. If CKTID is empty or null, the CKTID field will not be displayed.

<CMDMDE> is the command execution mode. NORM mode is the default behavior for all commands but you can specify FRCD to force the system to override a state in which the command would normally be denied.

For additional information, including valid command values, refer to the Cisco ONS SONET TL1 Command Guide or the Cisco ONS 15454 SDH and Cisco ONS 15600 SDH TL1 Command Guide.

d. In the TL1 dialog box, use the DLT-OCHCC command to delete the OCHCC cross-connects for the express path OCHCC listed in Step 4, using the following format:

DLT-OCHCC:[<TID>]:<AID>:<CTAG>[:::CKTID=<CKTID>],

where:

<AID> is the access identifier from the Channel section.

<CKTID> is the cross-connect ID. The default is Blank or None. CKTD is a string of ASCII characters. The maximum length is 48. If CKTID is empty or null, the CKTID field will not be displayed.

<CMDMDE> is the command execution mode. NORM mode is the default behavior for all commands but you can specify FRCD to force the system to override a state in which the command would normally be denied.

<PST> is the Primary state, which indicates the current overall service condition of an entity. The default is IS (in service).

<SST> s the Secondary state, which provides additional information pertaining to PST and PSTQ. The default is AINS.

For additional information, including valid command values, refer to the Cisco ONS SONET TL1 Command Guide or the Cisco ONS 15454 SDH and Cisco ONS 15600 SDH TL1 Command Guide.

e. Click Close to close the TL1 dialog box.

Step 9 Remove the fibers from the target node, and reconnect the fibers to the adjacent nodes.

Step 10 Update the ANS parameters at the adjacent nodes:

a. Display an adjacent node in node view.

b. Complete the "NTP-G143 Import the Cisco MetroPlanner NE Update Configuration File" procedure on page 3-39 to load the new NE Update file onto the node.

c. Complete the "NTP-G37 Run Automatic Node Setup" procedure on page 3-83 to recalculate the ANS parameters at the node.

d. Display the next adjacent node in node view.

e. Repeat Steps b and c for the second adjacent node.

Step 11 Repeat Step 7 to change the circuits placed in OOS,DSBLD (ANSI) or Locked,disabled (ETSI) back in service by changing the Target Circuit Admin State field to IS-AINS (ANSI) or Unlocked,AutomaticInService (ETSI).

Step 12 Complete the "DLP-G180 Clear a Manual or Force Y-Cable or Splitter Protection Switch" task on page 10-39 for the OCHNCs and/or OCHCCs that were switched in Step 6.

Step 13 Complete the "DLP-G346 Provision Optical Channel Client Connections" task on page 7-4 and/or the "DLP-G105 Provision Optical Channel Network Connections" task on page 7-11 to recreate OCHCCs and/or OCHNCs identified in Step 4 that originated or terminated on the removed DWDM node. Choose the new DWDM node as the start/end (add/drop, respectively) for each circuit.

Stop. You have completed this procedure.


NTP-G146 Add a Rack and/or Shelf to a Multishelf Node

Purpose

This procedure adds a rack and/or subtending shelf to a multishelf node.

Tools/Equipment

None

Prerequisite Procedures

One of the following:

NTP-G145 Connect a Multishelf Node and Subtending Shelves to an MS-ISC-100T Card, page 1-81, or

NTP-G158 Connect a Multishelf Node and Subtending Shelves to a Cisco Catalyst 2950, page 1-83

Chapter 3, "Turn Up a Node"

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

Provisioning or higher



Note Each shelf you want to add to a multishelf configuration must have network connectivity. For more information, see "Connect the PC and Log into the GUI."



Step 1 Complete the "DLP-G46 Log into CTC" task at the multishelf DWDM node where you want to add a shelf.

Step 2 To add a rack, in multishelf view, right click the gray area and choose Add Rack. If you do not need to add a rack, continue with Step 3.

Step 3 To add a shelf, in multishelf view, right-click the white space inside the rack and choose Add Shelf.

Step 4 In the Shelf ID Selection dialog box, choose a shelf ID from the drop-down list.

Step 5 Click OK. The shelf appears in the multishelf view.

Step 6 Complete the "DLP-G46 Log into CTC" task at the subtending shelf.

Step 7 In multishelf view, click the Provisioning > General > Multishelf Config tabs.

Step 8 Click Enable as Subtended Shelf.

Step 9 From the Shelf ID drop-down list, choose the shelf ID that you created in Step 4.

Step 10 Click Apply.

Step 11 In the confirmation dialog box, click Yes to reboot the shelf. The CTC view changes to network view and the node icon changes to gray. (This might take several minutes.)

Step 12 If you are connecting the new subtending shelf to the EAP patch panel, complete the following steps. If not, continue with Step 13.

a. Using a cross-over (CAT 5) LAN cable, plug one connector into the front panel of the subtending shelf TCC2/TCC2P card in Slot 7 and plug the other end into the SSC port on the left patch panel.

b. Using a cross-over (CAT 5) LAN cable, plug one connector into the front panel of the subtending shelf TCC2/TCC2P card in Slot 11 and plug the other end into the SSC port on the right patch panel.

Step 13 If you are connecting the subtending shelf to the Catalyst 2950 switch, complete the following steps. If not, continue with Step 14.

a. Plug one end of a cross-over (CAT-5) LAN cable into the front panel of the subtending shelf TCC2/TCC2P card in Slot 7 and plug the other end into Port 2 of the first Catalyst 2950.

b. Plug one end of a cross-over (CAT-5) LAN cable into the front panel of the subtending shelf TCC2/TCC2P card in Slot 11 and plug the other end into Port 2 of the backup Catalyst 2950.

Step 14 Repeat Steps 3 through 12 for each subtending shelf in the multishelf configuration.

Stop. You have completed this procedure.


NTP-G147 Delete a Shelf and/or Rack from a Multishelf Node

Purpose

This procedure deletes a shelf and/or rack from a multishelf node in the CTC window.

Tools/Equipment

None

Prerequisite Procedures

One of the following:

NTP-G145 Connect a Multishelf Node and Subtending Shelves to an MS-ISC-100T Card, page 1-81, or

NTP-G158 Connect a Multishelf Node and Subtending Shelves to a Cisco Catalyst 2950, page 1-83

Chapter 3, "Turn Up a Node"

Required/As Needed

As needed

Onsite/Remote

Onsite

Security Level

Provisioning or higher



Note You cannot delete a node controller shelf from a multishelf node configuration.



Step 1 Complete the "DLP-G46 Log into CTC" task at the multishelf DWDM node where you want to delete a shelf or rack. If you want to delete a shelf, continue with Step 2. If you want to delete a rack only, go to Step 9.

Step 2 Complete the following tasks, as needed:

If cards on the shelf carry unprotected circuits, you must delete the circuits. Complete the "DLP-G106 Delete Optical Channel Network Connections" task on page 7-14 or the or the "DLP-G347 Delete Optical Channel Client Connections" task on page 7-8.

If cards use internal patchcords, complete the "DLP-G355 Delete an Internal Patchcord" task on page 3-83.

If cards on the shelf are an OSCM or OSC-CSM with an OSC or GCC termination, complete the "NTP-G85 Modify or Delete OSC Terminations, GCC Terminations, and Provisionable Patchcords" procedure on page 10-42.

Put all ports in the Out-of-Service and Management, Disabled (OOS-MA,DSBLD) (ANSI) or Locked-enabled,disabled (ETSI) service state. For more information, see "Change DWDM Card Settings."


Note It is not necessary to delete the cards from the shelf before deleting a shelf.


Step 3 From the View menu, choose Go to Parent View to return to multishelf view.

Step 4 Right-click on the shelf in the rack for the subtending shelf you want to delete and choose Delete Shelf.

Step 5 In the confirmation dialog box, click Yes.

Step 6 To return the deleted shelf to a single-shelf node, you must use the LCD panel:

a. Repeatedly press the Status button until Shelf Status appears.

b. Repeatedly press the Port button until Controller Status=MS Config appears.

c. Press Status again and press Port to set multishelf mode to MS=N.

d. Press Status to choose Done.

e. Repeatedly press Status until "Save and Reboot?" appears, and then press Slot to choose Apply. This reboots the shelf. A "Saving changes; TCC may reboot" message appears on the LCD.

Step 7 After the TCC2/TCC2P reboot is complete, complete the following steps to disconnect the removed subtending shelf from the patch panel or Catalyst 2950.

a. Remove the cross-over (CAT 5) LAN cable from the front panel of the TCC2/TCC2P card in Slot 7.

b. Remove the cross-over (CAT 5) LAN cable from the front panel of the TCC2/TCC2P card in Slot 11.

Step 8 Reconnect the shelf to the LAN either on the backplane or one of the front panel TCC2/TCC2Ps. For more information, see "Connect the PC and Log into the GUI."

Step 9 To delete an empty rack from the CTC window, right-click in the gray area on the rack graphic and choose Delete Rack.

Stop. You have completed this procedure.