cc/td/doc/product/ong/15400/r34docs
hometocprevnextglossaryfeedbacksearchhelp
PDF

Table Of Contents

Install the Shelf and Backplane Cable

Before You Begin

Required Tools and Equipment

Included Materials

User-Supplied Materials

NTP-1 Unpack and Inspect the ONS 15454 Shelf Assembly

DLP-1 Unpack and Verify the Shelf Assembly

DLP-2 Inspect the Shelf Assembly

NTP-2 Install the Shelf Assembly

DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack

DLP-4 Install the External Brackets and Air Filter

DLP-5 Mount the Shelf Assembly in a Rack (One Person)

DLP-6 Mount the Shelf Assembly in a Rack (Two People)

DLP-7 Mount Multiple Shelf Assemblies in a Rack

NTP-3 Open and Remove the Front Door

DLP-8 Open the Front Cabinet Compartment (Door)

DLP-9 Remove the Front Door

NTP-4 Remove the Backplane Covers

DLP-10 Remove the Lower Backplane Cover

DLP-11 Remove the Backplane Sheet Metal Cover

NTP-5 Install the Electrical Interface Assemblies

DLP-12 Install a BNC or High-Density BNC EIA

DLP-13 Install an SMB EIA

DLP-14 Install the AMP Champ EIA

NTP-6 Install the Power and Ground

DLP-15 Verify that the Correct Fuse and Alarm Panel is Installed in the Equipment Rack

DLP-16 Connect the Office Ground to the ONS 15454

DLP-17 Connect Office Power to the ONS 15454 Shelf

DLP-18 Turn On and Verify Office Power

NTP-7 Install the Fan-Tray Assembly

NTP-119 Install the Alarm Expansion Panel

NTP-8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

DLP-19 Install Alarm Wires on the Backplane

DLP-20 Install Timing Wires on the Backplane

DLP-21 Install LAN Wires on the Backplane

DLP-22 Install the TL1 Craft Interface

NTP-120 Install an External Wire-Wrap Panel to the AEP

NTP-9 Install the Electrical Card Cables on the Backplane

DLP-23 Install DS-1 Cables Using Electrical Interface Adapters (Balun)

DLP-24 Install DS-1 AMP Champ Cables on the AMP Champ EIA

DLP-25 Install Coaxial Cable With BNC Connectors

DLP-26 Install Coaxial Cable With High-Density BNC Connectors

DLP-27 Install Coaxial Cable with SMB Connectors

NTP-10 Route Electrical Cables

DLP-28 Route Coaxial Cables

DLP-29 Route DS-1 Twisted-Pair Cables

NTP-11 Install the Rear Cover

NTP-12 Install Ferrites

DLP-30 Install Ferrites to Power Cabling

DLP-31 Attach Ferrites to Wire-Wrap Pin Fields

NTP-13 Perform the Shelf Installation Acceptance Test

DLP-32 Inspect the Shelf Installation and Connections

DLP-33 Measure Voltage


Install the Shelf and Backplane Cable


This chapter provides procedures for installing the Cisco ONS 15454. To view a summary of the tools and equipment required for installation, see the "Required Tools and Equipment" section.

Before You Begin

This section lists the chapter procedures (NTPs). Turn to a procedure for applicable tasks (DLPs).

1. NTP-1 Unpack and Inspect the ONS 15454 Shelf Assembly—Complete this procedure before continuing with the "NTP-2 Install the Shelf Assembly" procedure.

2. NTP-2 Install the Shelf Assembly—Complete this procedure to install the shelf assembly in a rack.

3. NTP-3 Open and Remove the Front Door—Complete this procedure to access the equipment before continuing with other procedures in this chapter.

4. NTP-4 Remove the Backplane Covers—Complete this procedure to access the backplane before continuing with other procedures in this chapter.

5. NTP-5 Install the Electrical Interface Assemblies—Complete this procedure if you plan to install electrical cards. This procedure is a prerequisite to the "NTP-9 Install the Electrical Card Cables on the Backplane" procedure.

6. NTP-6 Install the Power and Ground—Complete this procedure before continuing with the "NTP-7 Install the Fan-Tray Assembly" procedure.

7. NTP-7 Install the Fan-Tray Assembly—Complete this procedure to install the fan-tray assembly in the shelf.

8. NTP-119 Install the Alarm Expansion Panel—Complete this procedure if you are planning to install the Alarm Interface Controller-International (AIC-I) card and want to increase the number of alarm contacts provided by the AIC-I.

9. NTP-8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections—Complete this procedure to set up wire-wrap pin connections.

10. NTP-120 Install an External Wire-Wrap Panel to the AEP—Complete this procedure to connect an external wire-wrap panel to the AEP.

11. NTP-9 Install the Electrical Card Cables on the Backplane—Complete this procedure if you plan to install electrical cards.

12. NTP-10 Route Electrical Cables—Complete this procedure before continuing with the "NTP-11 Install the Rear Cover" procedure.

13. NTP-11 Install the Rear Cover—Complete this procedure to install the rear cover.

14. NTP-12 Install Ferrites—Complete this procedure to attach ferrites to power cables.

15. NTP-13 Perform the Shelf Installation Acceptance Test—Complete this procedure to determine if you have correctly completed all other procedures in the chapter.


Warning Only trained and qualified personnel should be allowed to install, replace, or service this equipment.



Warning The ONS 15454 is intended for installation in restricted access areas. A restricted access area is where access can only be gained by service personnel through the use of a special tool, lock, key, or other means of security. A restricted access area is controlled by the authority responsible for the location.



Warning The ONS 15454 is suitable for mounting on concrete or other non-combustible surfaces only.


Required Tools and Equipment

You will need the following tools and equipment to install and test the ONS 15454.

Included Materials

The following materials are required and are shipped with the ONS 15454 shelf (wrapped in plastic). The number in parentheses gives the quantity of the item included in the package.

#12-24 x 3/4 pan head Phillips mounting screws (48-1004-XX, 48-1007-XX) (8)

#12 -24 x 3/4 socket set screws (48-1003-XX) (2)

T-handle #12-24 hex tool for set screws (1)

ESD wrist strap with 1.8 m (6 ft) coil cable (1)

Tie wraps (10)

Pinned hex (Allen) key for front door (1)

Spacers (50-1193-XX) (4)

Spacer mounting brackets (2)

Clear plastic rear cover (1)

External (bottom) brackets for the fan-tray air filter

Standoff kit (53-0795-XX):

Plastic fiber management guides (2)

Fan filter bracket screws (53-48-0003) (6)

User-Supplied Materials

The following materials and tools are required but are not supplied with the ONS 15454.

Equipment rack (22 inches total width for a 19-inch rack; 26 inches total width for a 23-inch rack)

Fuse panel

Power cable (from fuse and alarm panel to assembly), #10 AWG, copper conductors, 194°F [90°C])


Note If you are installing power on a 15454-SA-NEBS3E, 15454-SA-NEBS3, or 15454-SA-R1, P/N: 800-07149 shelf assembly, the #12 to #14 AWG power cable is required.


Ground cable #6 AWG stranded


Note If you are installing power on a 15454-SA-NEBS3E, 15454-SA-NEBS3 or 15454-SA-R1, P/N: 800-07149 shelf assembly, the #14 AWG ground cable is required.


Alarm cable pairs for all alarm connections, #22 or #24 AWG, solid tinned

Shielded Building Integrated Timing Supply (BITS) clock cable pair #22 or #24, solid tinned

Single-mode SC fiber jumpers with UPC polish (55 dB or better) for optical (OC-N) cards

Shielded coaxial cable terminated with SMB or BNC connectors for DS-3 cards

Shielded ABAM cable terminated with AMP Champ connectors or unterminated for DS1N-14 cards with #22 or #24 AWG ground wire (typically about two feet in length)

6-pair #29 AWG double-shielded cable

Tie wraps and/or lacing cord

Labels

Listed pressure terminal connectors such as ring and fork types; connectors must be suitable for
#10 AWG copper conductors

Tools Needed

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Wire wrapper

Wire cutters

Wire strippers

Crimp tool

BNC insertion tool

Test Equipment

Voltmeter

Optical power meter (for use with fiber optics only)

Bit Error Rate (BER) tester, DS-1 and DS-3

NTP-1 Unpack and Inspect the ONS 15454 Shelf Assembly

Purpose

This procedure describes how to unpack the ONS 15454 and verify the contents.

Tools/Equipment

Pinned hex (Allen) key for front door

Prerequisite Procedures

None

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Complete the "DLP-1 Unpack and Verify the Shelf Assembly" task.

Step 2 Complete the "DLP-2 Inspect the Shelf Assembly" task.

Step 3 Continue with the "NTP-2 Install the Shelf Assembly" procedure.


DLP-1 Unpack and Verify the Shelf Assembly

Purpose

This task removes the shelf assembly from the package.

Tools/Equipment

None

Prerequisite Procedures

None

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 When you receive the ONS 15454 system equipment at the installation site, open the top of the box. The Cisco Systems logo designates the top of the box.

Step 2 Remove the foam inserts from the box. The box contains the 15454 shelf (wrapped in plastic) and a smaller box of items needed for installation.

Step 3 To remove the shelf, grasp both rings of the shelf removal strap and slowly lift the shelf out of the box.

Step 4 Open the smaller box of installation materials, and verify that you have all items listed in the "Included Materials" section.


Note The fan-tray assembly is shipped separately.


Step 5 Return to your originating procedure (NTP).


DLP-2 Inspect the Shelf Assembly

Purpose

This task verifies that all parts of the shelf assembly are in good condition.

Tools/Equipment

Pinned hex (Allen) key for front door

Prerequisite Procedures

DLP-1 Unpack and Verify the Shelf Assembly

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Open the shelf using the pinned hex key. For more information, see the "DLP-8 Open the Front Cabinet Compartment (Door)" task.

Step 2 Verify the following:

Pins are not bent or broken

Frame is not bent

Step 3 If the pins are bent or broken, or the frame is bent, call your Cisco sales engineer for a replacement.

Step 4 Close the front door before installing.

Step 5 Return to your originating procedure (NTP).


NTP-2 Install the Shelf Assembly

Purpose

This procedure describes how to reverse the mounting bracket and mount shelf assemblies in a rack.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Pinned hex key

Two set screws (48-1003-XX)

Prerequisite Procedures

NTP-1 Unpack and Inspect the ONS 15454 Shelf Assembly

Required/As Needed

Required

Onsite/Remote

Onsite



Warning To prevent the equipment from overheating, do not operate it in an area that exceeds the maximum recommended ambient temperature of 131°F (55°C). To prevent airflow restriction, allow at least 3 inches (7.6 cm) of clearance around the ventilation openings.



Note The 10 Gbps compatible shelf assembly (15454-SA-10G) and fan-tray assembly (15454-FTA3) are required with the ONS 15454 XC10G, OC-192, and OC-48 any slot (AS) cards.



Warning The ONS 15454 should be installed in the lower rack position or mounted above another ONS 15454 shelf assembly.



Warning The ONS 15454 must have 1 inch of airspace below the installed shelf assembly to allow air flow to the fan intake. The air ramp (the angled piece of sheet metal on top of the shelf assembly) provides this spacing and should not be modified in any way.



Step 1 Complete the "DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack" task if you need to convert from a 23-inch to a 19-inch rack.

Step 2 To install the air filter in an alternative location, complete the "DLP-4 Install the External Brackets and Air Filter" task.

Step 3 Complete the necessary rack mount task:

DLP-5 Mount the Shelf Assembly in a Rack (One Person)

DLP-6 Mount the Shelf Assembly in a Rack (Two People)

DLP-7 Mount Multiple Shelf Assemblies in a Rack

Step 4 Continue with the "NTP-3 Open and Remove the Front Door" procedure.


DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack

Purpose

This task installs the mounting bracket to convert a 23-inch rack to a 19-inch rack.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Prerequisite Procedures

None

Required/As Needed

As needed

Onsite/Remote

Onsite



Caution Use only the fastening hardware provided with the ONS 15454 to prevent loosening, deterioration, and electromechanical corrosion of the hardware and joined material.


Caution When mounting the ONS 15454 in a frame with a non-conductive coating (such as paint, lacquer, or enamel) either use the thread-forming screws provided with the ONS 15454 shipping kit, or remove the coating from the threads to ensure electrical continuity.


Step 1 Remove the screws that attach the mounting bracket to the side of the shelf assembly.

Step 2 Flip the detached mounting bracket upside down.

Text imprinted on the mounting bracket will now also be upside down.

Step 3 Place the widest side of the mounting bracket flush against the shelf assembly (see Figure 1-1).

The narrow side of the mounting bracket should be towards the front of the shelf assembly. Text imprinted on the mounting bracket should be visible and upside down.

Step 4 Align the mounting bracket screw holes against the shelf assembly screw holes.

Step 5 Insert the screws that were removed in Step 1 and tighten them.

Step 6 Repeat the task for the mounting bracket on the opposite side.

Figure 1-1 Reversing the mounting brackets (23-inch position to 19-inch position)

Step 7 Return to your originating procedure (NTP).


DLP-4 Install the External Brackets and Air Filter

The shelf assembly ships with external (bottom) brackets that you can use to install the air filter on the bottom of the shelf rather than beneath the fan-tray assembly. The brackets consist of two grooved metal pieces that attach to the bottom of the shelf assembly using three screws each. When you use the brackets to install the fan-tray air filter, you do not need to remove the fan-tray assembly to access the air filter. Attach the brackets to the bottom of the shelf assembly before installing the rack.

Although the filter will work if it is installed with either side facing up, Cisco recommends that you install it with the metal bracing facing up to preserve the surface of the filter.

Purpose

This task installs the external brackets and air filter.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Prerequisite Procedures

DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

Required/As Needed

As needed; perform this task if you want to access the air filter without removing the fan-tray assembly.

Onsite/Remote

Onsite



Note If you choose not to install the brackets, install the air filter by sliding it into the compartment at the bottom of the shelf assembly. Each time you remove and reinstall the air filter in the future, you must first remove the fan-tray assembly. Do not install an air filter in both filter locations on any shelf assembly.



Step 1 With the fan-tray assembly removed, place the ONS 15454 face down on a flat surface.

Step 2 Locate the three screw holes that run along the left and right sides of the bottom of the shelf assembly.

Step 3 Secure each bracket to the bottom of the shelf assembly using the screws (48-0003) provided in the backplane standoff kit (53-0795-XX).

Each bracket has a filter stopper and a flange on one end. Make sure to attach the brackets with the stoppers and flanges facing the rear of the shelf assembly (the top, if the ONS 15454 is face-down during installation).

Figure 1-2 illustrates bottom bracket installation. If you do not use the brackets, in the future you must remove the fan-tray assembly before removing the air filter. The brackets enable you to clean and replace the air filter without removing the fan-tray assembly.

Figure 1-2 Installing the external brackets

Step 4 Slide the air filter into the shelf assembly.

Step 5 Return to your originating procedure (NTP).


DLP-5 Mount the Shelf Assembly in a Rack (One Person)

Purpose

This task allows one person to mount the shelf assembly in a rack.

Tools/Equipment

Pinned hex key

Two set screws (48-1003-XX)

# 2 Phillips screwdriver

Prerequisite Procedures

DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

DLP-4 Install the External Brackets and Air Filter, if applicable

Required/As Needed

As needed

Onsite/Remote

Onsite



Step 1 Verify that the proper fuse and alarm panel has been installed in the top mounting space. If a fuse and alarm panel has not been installed, you must install one according to manufacturer's instructions.

If installing the 15454-SA-ANSI shelf assembly, a 100-amp fuse panel (30-amp fuse per shelf minimum) is required.

If installing the 15454-SA-NEBS3 shelf assembly, a standard 80-amp fuse panel (20-amp fuse per shelf minimum) is required.

Step 2 Ensure that the shelf assembly is set for the desired rack size (either 19 or 23 inches).

Step 3 Using the hex key that shipped with the assembly, install the two set screws into the screw holes that will not be used to mount the shelf.

Step 4 Lift the shelf assembly to the desired rack position and set it on the set screws.

Step 5 Align the screw holes on the mounting ears with the mounting holes in the rack.

Step 6 Using the Phillips screwdriver, install one mounting screw in each side of the assembly.

Step 7 When the shelf assembly is secured to the rack, install the remaining mounting screws.


Note Use at least one set of the horizontal screw slots on the ONS 15454 to prevent slippage.


Step 8 Remove the temporary set screws.

Step 9 Return to your originating procedure (NTP).


DLP-6 Mount the Shelf Assembly in a Rack (Two People)

Purpose

This task allows two people to mount the shelf assembly in a rack.

Tools/Equipment

Pinned hex key

Two set screws (48-1003-XX)

# 2 Phillips screwdriver

Prerequisite Procedures

DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

DLP-4 Install the External Brackets and Air Filter, if applicable

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Verify that the proper fuse and alarm panel has been installed in the top mounting space. If a fuse and alarm panel is not present, you must install one according to manufacturer's instructions.

If installing the 15454-SA-ANSI shelf assembly, a 100-amp fuse panel (30-amp fuse per shelf minimum) is required.

If installing the 15454-SA-NEBS3 shelf assembly, a standard 80-amp fuse panel (20-amp fuse per shelf minimum) is required.

Step 2 Ensure that the shelf assembly is set for the desired rack size (either 19 or 23 inches).

Step 3 Using the hex key that shipped with the shelf assembly, install the two set screws (48-1003-XX) into the screw holes that will not be used to mount the shelf.

Step 4 Lift the shelf assembly to the desired position in the rack.

Step 5 Align the screw holes on the mounting ears with the mounting holes in the rack.

Step 6 While one person holds the shelf assembly in place, the other person can install one mounting screw in each side of the assembly using the Phillips screwdriver.

Step 7 When the shelf assembly is secured to the rack, install the remaining mounting screws.


Note Use at least one set of the horizontal screw slots on the ONS 15454 to prevent slippage.


Step 8 Remove the temporary set screws.

Step 9 Return to your originating procedure (NTP).


DLP-7 Mount Multiple Shelf Assemblies in a Rack

Purpose

This task allows multiple shelves to be assembled in a rack.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Prerequisite Procedures

DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

DLP-4 Install the External Brackets and Air Filter, if applicable

Required/As Needed

As needed

Onsite/Remote

Onsite



Note The ONS 15454 must have one inch of airspace below the installed shelf assembly to allow air flow to the fan intake. If a second ONS 15454 is installed underneath a shelf assembly, the air ramp on top of the bottom shelf assembly provides the desired space. However, if the ONS 15454 is installed above third-party equipment, you must provide a minimum spacing of one inch between the third-party shelf assembly and the bottom of the ONS 15454. The third-party equipment must not vent heat upward into the ONS 15454.



Step 1 Verify that the proper fuse and alarm panel has been installed in the top mounting space. If a fuse and alarm panel is not present, you must install one according to manufacturer's instructions.

If installing the 15454-SA-ANSI shelf assembly, a 100-amp fuse panel (30-amp fuse per shelf minimum) is required.

If installing the 15454-SA-NEBS3 shelf assembly, a standard 80-amp fuse panel (20-amp fuse per shelf minimum) is required.

Step 2 Mount the first ONS 15454 directly below the fuse and alarm panel using the "DLP-5 Mount the Shelf Assembly in a Rack (One Person)" task or the "DLP-6 Mount the Shelf Assembly in a Rack (Two People)" task.

Step 3 Repeat the task with the second and third (fourth if applicable) ONS 15454s.

Step 4 Return to your originating procedure (NTP).


NTP-3 Open and Remove the Front Door

Purpose

This procedure describes how to open and remove the front door to access the equipment.

Tools/Equipment

Open end wrench

Pinned hex key

Prerequisite Procedures

NTP-2 Install the Shelf Assembly

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Complete the "DLP-8 Open the Front Cabinet Compartment (Door)" task.

Step 2 Complete the "DLP-9 Remove the Front Door" task.

Step 3 Continue with the "NTP-4 Remove the Backplane Covers" procedure.


DLP-8 Open the Front Cabinet Compartment (Door)

Purpose

This task opens the front cabinet compartment door.

Tools/Equipment

Pinned hex key

Prerequisite Procedures

DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

DLP-4 Install the External Brackets and Air Filter, if applicable

DLP-5 Mount the Shelf Assembly in a Rack (One Person) or DLP-6 Mount the Shelf Assembly in a Rack (Two People)

DLP-7 Mount Multiple Shelf Assemblies in a Rack, if applicable

Required/As Needed

Required

Onsite/Remote

Onsite



Note The ONS 15454 has an ESD plug input and is shipped with an ESD wrist strap. The ESD plug input is located on the outside edge of the shelf assembly on the right-hand side. It is labeled "ESD" on the top and bottom. Always wear an ESD wrist strap and connect the strap to the ESD plug when working on the ONS 15454.



Step 1 Open the front door lock ( Figure 1-3).

The ONS 15454 comes with a pinned hex key for locking and unlocking the front door. Turn the key counterclockwise to unlock the door and clockwise to lock it.

Step 2 Press the door button to release the latch.

Step 3 Swing the door open.

Figure 1-3 The ONS 15454 front door

Step 4 Return to your originating procedure (NTP).


DLP-9 Remove the Front Door

Purpose

This task removes the front cabinet compartment door.

Tools/Equipment

Open end wrench

Prerequisite Procedures

DLP-8 Open the Front Cabinet Compartment (Door)

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Open the door.

Step 2 To remove the door ground strap (available in Release 3.3 and later), perform the following:

a. To detach the ground strap from the front door, loosen the #6 Kepnut (49-0600-01) using the open end wrench. Detach the end of the ground strap terminal lug (72-3622-01) from the male stud on the inside of the door.

b. To detach the other end of the ground strap from the longer screw on the fiber guide, loosen the #4 Kepnut (49-0337-01) on the terminal lug using the open end wrench. Remove the terminal lug and lock washer.

Step 3 Lift the door from its hinges at the top left-hand corner of the door ( Figure 1-4).

Figure 1-4 Removing the ONS 15454 front door

Step 4 Return to your originating procedure (NTP).


NTP-4 Remove the Backplane Covers

Purpose

This procedure describes how to access the backplane by removing the covers. The backplane has two sheet metal covers (one on either side) and a lower backplane cover at the bottom.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Prerequisite Procedures

NTP-2 Install the Shelf Assembly

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Complete the "DLP-10 Remove the Lower Backplane Cover" task.

Step 2 Complete the "DLP-11 Remove the Backplane Sheet Metal Cover" task.

Step 3 If you plan to install Electrical Interface Assemblies (EIAs), continue with the "NTP-5 Install the Electrical Interface Assemblies" procedure. If not, continue with the "NTP-6 Install the Power and Ground" procedure.


DLP-10 Remove the Lower Backplane Cover

Purpose

This task removes the lower backplane cover.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Prerequisite Procedures

DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

DLP-4 Install the External Brackets and Air Filter, if applicable

DLP-5 Mount the Shelf Assembly in a Rack (One Person) or DLP-6 Mount the Shelf Assembly in a Rack (Two People)

DLP-7 Mount Multiple Shelf Assemblies in a Rack, if applicable

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Unscrew the five retaining screws that hold the clear plastic cover in place.

Step 2 Grasp the clear plastic cover on each side.

Step 3 Gently pull the cover away from the backplane.

Step 4 Return to your originating procedure (NTP).


DLP-11 Remove the Backplane Sheet Metal Cover

Purpose

This task removes the backplane sheet cover that is installed on the backplane when EIAs are not installed.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Prerequisite Procedures

DLP-3 Reverse the Mounting Bracket to Fit a 19-inch Rack, if applicable

DLP-4 Install the External Brackets and Air Filter, if applicable

DLP-5 Mount the Shelf Assembly in a Rack (One Person) or DLP-6 Mount the Shelf Assembly in a Rack (Two People)

DLP-7 Mount Multiple Shelf Assemblies in a Rack, if applicable

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 To remove the lower clear plastic backplane cover, loosen the five screws that secure it to the ONS 15454 and pull it away from the shelf assembly.

Step 2 Loosen the nine perimeter screws that hold the backplane sheet metal cover(s) in place.

Step 3 Lift the panel by the bottom to remove it from the shelf assembly.

Step 4 Store the panel for later use. Attach the backplane cover(s) whenever EIA(s) are not installed.

Step 5 Return to your originating procedure (NTP).


NTP-5 Install the Electrical Interface Assemblies

Purpose

This procedure describes how to install electrical interface assemblies (EIAs). Typically an EIA panel is already installed on the backplane when the node is received, but EIA panels can be ordered separately. Refer to the Cisco ONS 15454 Reference Manual for descriptions of the EIAs.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

9 perimeter screws

12 inner screws

5 backplane cover screws

EIA card (SMB, BNC, AMP Champ)

EIA panel

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required if the node will use electrical signals

Onsite/Remote

Onsite



Caution Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the wristband cable into the ESD jack located on the lower-right outside edge of the shelf assembly.


Note EIAs are normally factory installed. Verify that the correct EIA is installed on the shelf assembly. If not, install the correct EIA.



Step 1 Complete the "DLP-12 Install a BNC or High-Density BNC EIA" task as needed. BNCs are locking connectors; the high-density BNC also allows you to access every port on every card.

Step 2 Complete the "DLP-13 Install an SMB EIA" task as needed. SMBs allow you to access every port on every card using more space and efficient cabling.

Step 3 Complete the "DLP-14 Install the AMP Champ EIA" task as needed. AMP champs are exclusive to DS-1 cables.


Note To attach cables to the EIAs, see the "NTP-9 Install the Electrical Card Cables on the Backplane" procedure.


Step 4 Continue with the "NTP-6 Install the Power and Ground" procedure.


DLP-12 Install a BNC or High-Density BNC EIA

Purpose

This task installs a BNC or high-density BNC EIA.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

9 perimeter screws

12 inner screws

5 backplane cover screws

BNC or high-density BNC card

EIA cover

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required if you are using DS3-12, DS3XM-6, or EC-1 cards and prefer a BNC interface to an SMB interface

Onsite/Remote

Onsite



Step 1 Remove the BNC or high-density BNC card from the packaging. Line up the connectors on the card with the mating connectors on the backplane. Gently push the card until both sets of connectors fit together snugly.

Step 2 Place the metal EIA panel over the card.

Step 3 Insert and tighten the nine perimeter screws (P/N 48-0358) at 8-10 lbs to secure the cover panel to the backplane.

Step 4 Insert and tighten the twelve (BNC) or nine (high-density BNC) inner screws (P/N 48-0004) at 8-10 lbs to secure the cover panel to the card and backplane.

Figure 1-5 shows a BNC EIA installation. Figure 1-6 shows high-density BNC EIA installation.

Figure 1-5 Installing the BNC EIA

Figure 1-6 Installing the high-density BNC EIA

Step 5 Return to your originating procedure (NTP).


DLP-13 Install an SMB EIA

Purpose

This task installs an SMB EIA.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

9 perimeter screws

12 inner screws

5 backplane cover screws

SMB card

EIA panel

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required if you are using DS1-14 cards and prefer an SMB interface to an AMP interface; or if you are using DS3-12, DS3XM-6, or EC-1 cards and prefer an SMB interface to a BNC interface

Onsite/Remote

Onsite



Step 1 Remove the SMB card from the packaging. Line up the connectors on the card with the mating connectors on the backplane. Gently push the card until both sets of connectors fit together snugly.

Step 2 Place the EIA panel over the card.

Step 3 Insert and tighten the nine perimeter screws (P/N 48-0358) at 8-10 lbs to secure the cover panel to the backplane.

Step 4 Insert and tighten the twelve inner screws (P/N 48-0004) at 8-10 lbs to secure the cover panel to the card and backplane.

If you are using SMB EIAs to make DS-1 connections, you need the DS-1 electrical interface adapter, commonly referred to as a balun (P/N 15454-WW-14=).

Step 5 Return to your originating procedure (NTP).


DLP-14 Install the AMP Champ EIA

Purpose

This task installs an AMP Champ EIA.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

9 perimeter screws

12 inner screws

5 backplane cover screws

6 AMP Champ cards

EIA panel

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required if you are using DS1-14 cards and prefer an AMP interface to an SMB interface

Onsite/Remote

Onsite



Step 1 Align the AMP Champ panel with the backplane and insert and tighten the nine perimeter screws (P/N 48-0358) at 8-10 lbs.

Step 2 Align an AMP Champ card with the backplane connector and push until it fits snugly. Repeat until you have installed all six AMP Champ cards.

Step 3 To secure each AMP Champ card to the cover panel, insert and tighten a screw (P/N 48-0003) at the top of each card at 8-10 lbs.

Step 4 Place the AMP Champ fastening plate along the bottom of the cover panel, and hand tighten the two thumbscrews.

Figure 1-7 shows an AMP Champ EIA installation.

Figure 1-7 Installing the AMP Champ EIA

Step 5 Return to your originating procedure (NTP).


NTP-6 Install the Power and Ground

Purpose

This procedure describes how to install power feeds and ground the ONS 15454.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Screws

Power cable (from fuse and alarm panel to assembly), #10 AWG, copper conductors, 194°F [90°C])

Ground cable #6 AWG stranded

Listed pressure terminal connectors such as ring and fork types; connectors must be suitable for #10 AWG copper conductors

Wire wrapper

Wire cutters

Wire strippers

Crimp tool

Fuse panel

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required

Onsite/Remote

Onsite



Warning Shut off the power from the power source or turn off the breakers before beginning work.



Warning This equipment is intended to be grounded. Ensure that the host is connected to earth ground during normal use.



Caution Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the wristband cable into the ESD jack located on the lower-right outside edge of the shelf assembly.


Warning Do not mix conductors of dissimilar metals in a terminal or splicing connector where physical contact occurs (such as copper and aluminum, or copper and copper-clad aluminum), unless the device is suited for the purpose and conditions of use.



Warning Connect the ONS 15454 only to a DC power source that complies with the safety extra-low voltage (SELV) requirements in IEC 60950-based safety standards.



Warning The ONS 15454 relies on the protective devices in the building installation to protect against short circuit, overcurrent, and grounding faults. Ensure that the protective devices are properly rated to protect the system, and that they comply with national and local codes.



Warning A readily accessible two-poled disconnect device must be incorporated in the fixed wiring.



Warning When installing redundant power feeds, do not use aluminum conductors.



Warning If you use redundant power leads to power the ONS 15454, disconnecting one lead will not remove power from the node.



Step 1 Complete the "DLP-15 Verify that the Correct Fuse and Alarm Panel is Installed in the Equipment Rack" task.

Step 2 Complete the "DLP-16 Connect the Office Ground to the ONS 15454" task.

Step 3 Complete the "DLP-17 Connect Office Power to the ONS 15454 Shelf" task.

Step 4 Complete the "DLP-18 Turn On and Verify Office Power" task.

Step 5 Continue with the "NTP-7 Install the Fan-Tray Assembly" procedure.


DLP-15 Verify that the Correct Fuse and Alarm Panel is Installed in the Equipment Rack

Purpose

This task verifies that the proper fuse and alarm panel is installed in the equipment rack.

Tools/Equipment

None

Prerequisite Procedures

None

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Verify the following:

If using the 15454-SA-ANSI shelf, a 100-amp fuse panel (30-amp fuse per shelf minimum) is installed. If not, install one according to manufacturer's instructions.

If using the 15454-SA-NEBS3 shelf, a standard 80-amp fuse panel (20-amp fuse per shelf minimum) is installed. If not, install one according to manufacturer's instructions.

Step 2 Return to your originating procedure (NTP).


DLP-16 Connect the Office Ground to the ONS 15454

Purpose

This task connects ground to the ONS 15454 shelf.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Screws

Power cable (from fuse and alarm panel to assembly), #10 AWG, copper conductors, 194°F [90°C])

Ground cable #6 AWG stranded

Listed pressure terminal connectors such as ring and fork types; connectors must be suitable for #10 AWG copper conductors

Prerequisite Procedures

DLP-10 Remove the Lower Backplane Cover

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Verify that the office ground cable (#6 AWG stranded) is connected to the top of the bay according to local site practice.

Step 2 Attach one end of the shelf ground cable (#6 AWG) to the right side of the backplane ground nut. See Figure 1-8 for the location of the ground on the backplane.


Note When terminating a frame ground, use the kep-nut provided with the ONS 15454 and tighten it to a torque specification of 31 in-lbs. The kep-nut provides a frame ground connection that minimizes the possibility of loosening caused by rotation during installation and maintenance activity. The type of prevention the kep-nut provides for the frame ground connection is inherently provided by the terminal block for battery and battery return connections.


Figure 1-8 Ground location on the backplane

Step 3 Attach the other end of the shelf ground cable to the bay.

Step 4 Return to your originating procedure (NTP).


DLP-17 Connect Office Power to the ONS 15454 Shelf

Purpose

This task connects power to the ONS 15454 shelf.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Wire wrapper

Wire cutters

Wire strippers

Crimp tool

Fuse panel

Power cable (from fuse and alarm panel to assembly), #10 AWG, copper conductors, 194°F [90°C])

Ground cable #6 AWG stranded

Listed pressure terminal connectors such as ring and fork types; connectors must be suitable for #10 AWG copper conductors

Prerequisite Procedures

DLP-15 Verify that the Correct Fuse and Alarm Panel is Installed in the Equipment Rack

DLP-16 Connect the Office Ground to the ONS 15454

Required/As Needed

Required

Onsite/Remote

Onsite



Note If the system loses power or both TCC+ cards are reset and the system is not provisioned to get the time from an NTP/SNTP server, you must reset the ONS 15454 clock. After powering down, the date defaults to January 1, 1970, 00:04:15. To reset the clock, see the "NTP-25 Set Up Name, Date, Time, and Contact Information" procedure.



Note If you encounter problems with the power supply, refer to the Cisco ONS 15454 Troubleshooting Guide.



Warning Do not apply power to the ONS 15454 until you complete all installation steps and check the continuity of the -48 VDC and return.



Step 1 Connect the office power according to the fuse panel engineering specifications.

Step 2 Measure and cut the cables as needed to reach the ONS 15454 from the fuse panel. Figure 1-9 shows the ONS 15454 power terminals.

Step 3 Dress the power according to local site practice.


Warning When installing the ONS 15454, the ground connection must always be made first and disconnected last.

Figure 1-9 ONS 15454 power terminals

Step 4 Remove or loosen the #8 power terminal screws on the ONS 15454. To avoid confusion, label the cables connected to the BAT1/RET1 (A) power terminals as 1, and the cables connected to the BAT2/RET2 (B) power terminals as 2.


Note Use only pressure terminal connectors, such as ring and fork types, when terminating the battery, battery return, and frame ground conductors.



Caution Before you make any crimp connections, coat all bare conductors (battery, battery return, and frame ground) with an appropriate antioxidant compound. Bring all unplated connectors, braided strap, and bus bars to a bright finish, then coat with an antioxidant before you connect them. You do not need to prepare tinned, solder-plated, or silver-plated connectors and other plated connection surfaces, but always keep them clean and free of contaminants.

Caution When terminating power, return, and frame ground, do not use soldering lug, screwless (push-in) connectors, quick-connect, or other friction-fit connectors.

Step 5 Strip 1/2 inch of insulation from all power cables that you will use.

Step 6 Crimp the lugs onto the ends of all power leads.


Note When terminating battery and battery return connections as shown in Figure 1-9, follow a torque specification of 10 in-lbs.


Step 7 Terminate the return 1 lead to the RET1 backplane terminal. Use oxidation-prevention grease to keep connections non-corrosive.


Warning Do not secure multiple connectors with the same bolt assembly.

Step 8 Terminate the negative 1 lead to the negative BAT1 backplane power terminal. Use oxidation prevention grease to keep connections non-corrosive.

Step 9 If you use redundant power leads, terminate the return 2 lead to the positive RET2 terminal on the ONS 15454. Terminate the negative 2 lead to the negative BAT2 terminal on the ONS 15454. Use oxidation-preventative grease to keep connections non-corrosive.

Step 10 Route the cables out below the power terminals using the plastic cable clamp, as shown in Figure 1-9.

Step 11 Return to your originating procedure (NTP).


DLP-18 Turn On and Verify Office Power

Purpose

This task measures the power to verify correct power and returns.

Tools/Equipment

Voltmeter

Prerequisite Procedures

DLP-15 Verify that the Correct Fuse and Alarm Panel is Installed in the Equipment Rack

DLP-16 Connect the Office Ground to the ONS 15454

DLP-17 Connect Office Power to the ONS 15454 Shelf

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Using a voltmeter, verify the office battery and ground at the following points on the fuse and alarm panel:

a. To verify the power, place the black test lead of the voltmeter to the frame ground. Place the red test lead on the A-side connection and verify that it is between -42 VDC and -57 VDC. Place the red test lead on the B-side connection and verify that it is between -42 VDC and -57 VDC.


Note The voltages -42 VDC and -57 VDC are, respectively, the minimum and maximum amperages required to power the chassis.


b. To verify the ground, place the black test lead of the voltmeter to the frame ground. Place the red test lead on the A-side return ground and verify that no voltage is present. Place the red test lead on the B-side return ground and verify that no voltage is present.

Step 2 Complete one of the following to power up the node:

If you are using a 80-amp fuse panel, insert a 20-amp fuse into the fuse position according to site practice.

If you are using a 100-amp fuse panel, insert a 30-amp fuse into the fuse position according to site practice.

Step 3 Using a voltmeter, verify the shelf for -48 VDC battery and ground:

a. To verify the A-side of the shelf, place the black lead of the voltmeter to the frame ground. Place the red test lead to the BAT1 (A-side battery connection) red cable. Verify it reads between -42 VDC and -57 VDC. Then place the red test lead of the voltmeter to the RET1 (A-side return ground) black cable and verify that no voltage is present.


Note The voltages -42 VDC and -57 VDC are, respectively, the minimum and maximum amperages required to power the chassis.


b. To verify the B-side of the shelf, place the black test lead of the voltmeter to the frame ground. Place the red test lead to the BAT2 (B-side battery connection) red cable. Verify it reads between -42 VDC and -57 VDC. Then place the red test lead of the voltmeter to the RET2 (B-side return ground) black cable and verify that no voltage is present.

Step 4 Return to your originating procedure (NTP).


NTP-7 Install the Fan-Tray Assembly

Purpose

This procedure installs the fan-tray assembly.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Prerequisite Procedures

NTP-3 Open and Remove the Front Door

NTP-6 Install the Power and Ground

Required/As Needed

Required

Onsite/Remote

Onsite



Caution Do not operate an ONS 15454 without a fan-tray air filter. A fan-tray air filter is mandatory.


Caution The 15454-FTA3 fan-tray assembly can only be installed in ONS 15454 Release 3.1 or later shelf assemblies (15454-SA-ANSI, 800-19857). It includes a pin that does not allow it to be installed in ONS 15454 shelf assemblies released before ONS 15454 Release 3.1 (15454-SA-NEBS3E, 15454-SA-NEBS3, and 15454-SA-R1, P/N 800-0714915454). Installing the 15454-FTA3 in a non-compliant shelf assembly may result in failure of the alarm interface panel (AIP), which in turn, will result in power loss to the fan-tray assembly.


Caution You must place the edge of the air filter flush against the front of the fan-tray assembly compartment when installing the fan tray on top of the filter. Failure to do so could result in damage to the filter, the fan tray, or both.


Caution Do not force a fan-tray assembly into place. Doing so can damage the connectors on the fan tray and/or the connectors on the back panel of the shelf assembly.


Note To install the fan-tray assembly, it is not necessary to move any of the cable-management facilities.



Step 1 Slide the fan tray into the shelf assembly until the electrical plug at the rear of the tray plugs into the corresponding receptacle on the backplane.

Step 2 To verify that the tray has plugged into the backplane, check that the LCD on the front of the fan tray is activated and displays data.

Figure 1-10 shows the location of the fan tray.

Figure 1-10 Installing the fan-tray assembly

Step 3 Continue with the "NTP-119 Install the Alarm Expansion Panel" procedure if you plan to install an Alarm Expansion Panel (AEP). If not, continue with the "NTP-8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections" procedure.


NTP-119 Install the Alarm Expansion Panel

Purpose

This procedure installs an Alarm Expansion Panel (AEP) onto the 15454-SA-ANSI shelf backplane that provides alarm contacts in addition to the 16 provided by the AIC-I card. Typically, the AEP is pre-installed when ordered with the ONS 15454; however, the AEP can be ordered separately.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Wire wrapper

6-pair #29 AWG double-shielded cable

Standoffs (4)

Prerequisite Procedures

DLP-10 Remove the Lower Backplane Cover

Required/As Needed

Required if you are terminating more than 16 alarm contacts (16 inputs + 0 outputs or 12 inputs or 4 outputs); the AIC-I card must be installed before you can provision the alarm contacts enabled by the AEP.

Onsite/Remote

Onsite



Note The AIC-I card provides direct alarm contacts (external alarm inputs and external control outputs). In the ANSI shelf, these AIC-I alarm contacts are routed through the backplane to wire-wrap pins accessible from the back of the shelf. When you install an AEP, the direct AIC-I alarm contacts cannot be used. Only the AEP alarm contacts can be used.



Step 1 Remove the two backplane screws. Replace the two screws with standoffs. Insert the longer standoff on the left, and the shorter standoff on the right ( Figure 1-11).

Figure 1-11 Replace backplane screws with standoffs

Step 2 Attach the remaining two standoffs on either side of the backplane ( Figure 1-12).

Step 3 Position the AEP board over the standoffs ( Figure 1-12).

Figure 1-12 Installing standoffs and the AEP

Step 4 Insert and tighten three screws to secure the AEP to the backplane.

Step 5 Attach the open ends of the wires from the AEP board to the wire-wrap pins on the backplane of the shelf ( Figure 1-13). Table 1-1 lists the AEP pin assignments.

Figure 1-13 AEP wire-wrap connections to backplane pins

Table 1-1 Pin Assignments for the AEP 

Wire
Pin
AEP signal
AIC-I signal

Tip 1

7

AEP_GND

GND

Tip 2

8

AEP_+5

AE_+5

Tip 3

9

VBAT-

VBAT-

Tip 4

10

VB+

VB+

Tip 6

6

AE_CLK_P

AE_CLK_P

Tip 7

5

AE_CLK_N

AE_CLK_N

Tip 8

4

AE_DOUT_P

AE_DIN_P

Tip 9

3

AE_DOUT_N

AE_DIN_N

Tip 10

2

AE_DIN_P

AE_DOUT_P

Tip 11

1

AE_DIN_N

AE_DOUT_N


Step 6 Attach the connector on the opposite end of the cable assembly to the RS-485 connector port on the AEP ( Figure 1-12).

Step 7 Continue with the "NTP-8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections" procedure.


NTP-8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

Purpose

This procedure describes how to install alarm, timing, LAN, and craft wires.

Tools/Equipment

Wire wrapper

#22 or #24 AWG alarm wires

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

As needed

Onsite/Remote

Onsite



Step 1 Complete the "DLP-19 Install Alarm Wires on the Backplane" task as necessary (if you are using an AIC or AIC-I card and not using an AEP).

Step 2 Complete the "DLP-20 Install Timing Wires on the Backplane" task as needed. Timing wires are necessary to provision external timing.

Step 3 Complete the "DLP-21 Install LAN Wires on the Backplane" task as needed. LAN wires (or the LAN port on the TCC+) are necessary to create an external LAN connection.

Step 4 Complete the "DLP-22 Install the TL1 Craft Interface" task as needed. Craft wires (or the RS-232 port on the TCC+) are required to access TL1 using the craft interface.


Caution Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the wristband cable into the ESD jack located on the lower-right outside edge of the shelf assembly.

Step 5 Complete one of the following:

If you installed an Alarm Expansion Panel (AEP), continue with the "NTP-120 Install an External Wire-Wrap Panel to the AEP" procedure.

If you did not install an AEP and you plan to install electrical cards, continue with the "NTP-9 Install the Electrical Card Cables on the Backplane" procedure.

If you did not install an AEP and do not plan to install electrical cards, continue with the "NTP-11 Install the Rear Cover" procedure.


DLP-19 Install Alarm Wires on the Backplane

Purpose

This task installs alarm wires on the backplane so that you can provision external (environmental) alarms and controls with the AIC or AIC-I card. If you are using the AEP, do not perform this task.

Tools/Equipment

Wire wrapper

#22 or #24 AWG wires

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required to create external alarms and controls without the AEP

Onsite/Remote

Onsite



Step 1 Use #22 or #24 AWG wires.

Step 2 Wrap the alarm wires on the appropriate wire-wrap pins according to local site practice. Figure 1-14 shows alarm pin assignments for the Release 3.4 ONS 15454 backplane. Figure 1-15 shows alarm pin assignments for the backplane used for Release 3.3 and earlier.

For information about attaching ferrites to wire-wrap pin fields, see the "NTP-12 Install Ferrites" section.

Figure 1-14 ONS 15454 backplane pinouts (Release 3.4)

Figure 1-15 ONS 15454 backplane pinouts (Release 3.3 and earlier)


Note The X.25, Modem, and TBOS pin fields are not active.


Step 3 Return to your originating procedure (NTP).


DLP-20 Install Timing Wires on the Backplane

Purpose

This task installs the timing wires on the backplane.

Tools/Equipment

Wire wrapper

#22 or #24 AWG wire

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required if the node is using external BITS timing

Onsite/Remote

Onsite



Step 1 Use #22 or #24 AWG wire.

Step 2 Wrap the clock wires on the appropriate wire-wrap pins according to local site practice.

The BITS pin field (FG1) has a frame ground pin beneath it. Wrap the ground shield of the alarm cable to the frame ground pin. Table 1-2 lists the pin assignments for the BITS timing pin fields.

Table 1-2 External Timing Pin Assignments for BITS 

External Device
Contact
Tip & Ring
Function

First external device

A3 (BITS 1 Out)

Primary ring (-)

Output to external device

B3 (BITS 1 Out)

Primary tip (+)

Output to external device

A4 (BITS 1 In)

Secondary ring (-)

Input from external device

B4 (BITS 1 In)

Secondary tip (+)

Input from external device

Second external device

A1 (BITS 2 Out)

Primary ring (-)

Output to external device

B1 (BITS 2 Out)

Primary tip (+)

Output to external device

A2 (BITS 2 In)

Secondary ring (-)

Input from external device

B2 (BITS 2 In

Secondary tip (+)

Input from external device



Note For more detailed information about timing, refer to the Cisco ONS 15454 Reference Manual. To set up system timing, see the "NTP-28 Set Up Timing" procedure.


Step 3 Return to your originating procedure (NTP).


DLP-21 Install LAN Wires on the Backplane

Purpose

This task installs the LAN wires on the backplane.

Tools/Equipment

Wire wrapper

#22 or #24 AWG wire

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required if the node is using an external LAN connection

Onsite/Remote

Onsite



Note Rather than using the LAN wires, you can use the LAN connection port on the TCC+ if preferred. Use either the backplane connection or the TCC+ front connection. You cannot use the LAN backplane pins and the LAN connection port on the TCC+ simultaneously; however, it is possible for you to make a direct connection from a computer to the LAN connection port on the TCC+ while the LAN backplane pins are in use as long as the computer connected directly to the TCC+ is not connected to a LAN.



Step 1 Use #22 or #24 AWG wire.

Step 2 Wrap the wires on the appropriate wire-wrap pins according to local site practice.


Caution Cross talk may result if both Rx and Tx pins connect on the same twisted pair of wires from the CAT 5 cable. The two Tx pins need to be on one twisted pair, and the two Rx pins need to be on another twisted pair.

A frame ground pin is located beneath each pin field (FG2 for the LAN pin field). Wrap the ground shield of the LAN interface cable to the frame ground pin. Table 1-3 shows the LAN pin assignments.

Table 1-3 LAN Pin Assignments

Pin Field
Backplane Pins
RJ-45 Pins

LAN 1
Connecting to data circuit-terminating equipment (DCE*) (a hub or switch)

B2

1

A2

2

B1

3

A1

6

LAN 1
Connecting to data terminal equipment (DTE) (a PC/workstation or router)

B1

1

A1

2

B2

3

A2

6


Step 3 Return to your originating procedure (NTP).


DLP-22 Install the TL1 Craft Interface

Purpose

This task installs the TL1 craft interface.

Tools/Equipment

Wire wrapper

#22 or #24 AWG alarm wires

Prerequisite Procedures

NTP-4 Remove the Backplane Covers

Required/As Needed

Required to access TL1 using the craft backplane pins

Onsite/Remote

Onsite



Note Rather than using the craft pins, you can use a LAN cable connected to the TCC+ RS-232 port to access a TL1 craft interface.



Step 1 Use #22 or #24 AWG wire.

Step 2 Wrap the craft interface wires on the appropriate wire-wrap pins according to local site practice.


Note For information about attaching ferrites to wire-wrap pin fields, see the "DLP-31 Attach Ferrites to Wire-Wrap Pin Fields" task.


Step 3 Wrap the ground shield of the craft interface cable to the frame-ground pin.

Wrap the ground wire of your computer cable to pin A3 on the craft pin field. Table 1-4 shows the pin assignments for the CRAFT pin field.


Note You cannot use the craft backplane pins and the RS-232 port on the TCC+ card simultaneously. Using a combination prevents access to the node or causes a loss in connectivity.


Table 1-4 Craft Interface Pin Assignments

Pin Field
Contact
Function

Craft

A1

Receive

A2

Transmit

A3

Ground

A4

DTR


Step 4 Return to your originating procedure (NTP).


NTP-120 Install an External Wire-Wrap Panel to the AEP

Purpose

This procedure connects an external wire-wrap panel to the Alarm Expansion Panel (AEP) to provide the physical alarm contacts for the AEP.

Tools/Equipment

External wire-wrap panel

Prerequisite Procedures

NTP-119 Install the Alarm Expansion Panel

Required/As Needed

Required if you installed an AEP

Onsite/Remote

Onsite



Step 1 Position the lower cover over the AEP. Make sure that the AEP AMP Champ connectors protrude through the cut-outs in the lower cover ( Figure 1-16).

Figure 1-16 Installing the AEP cover

Step 2 Insert and tighten the eight screws to secure the AEP cover to the AEP.

Step 3 Connect the cables from the external wire-wrap panel to the AMP Champ connectors on the AEP. Table 1-5 lists the alarm input pin assignments. Table 1-6 lists the alarm output pin assignments. Figure 1-17 and Figure 1-18 illustrate the alarm input and output connectors, respectively.

Table 1-5 Alarm Input Pin Assignments 

AMP Champ Pin
Signal name
AMP Champ Pin
Signal name

1

ALARM_IN_1-

27

GND

2

GND

28

ALARM_IN_2-

3

ALARM_IN_3-

29

ALARM_IN_4-

4

ALARM_IN_5-

30

GND

5

GND

31

ALARM_IN_6-

6

ALARM_IN_7-

32

ALARM_IN_8-

7

ALARM_IN_9-

33

GND

8

GND

34

ALARM_IN_10-

9

ALARM_IN_11-

35

ALARM_IN_12-

10

ALARM_IN_13-

36

GND

11

GND

37

ALARM_IN_14-

12

ALARM_IN_15-

38

ALARM_IN_16-

13

ALARM_IN_17-

39

GND

14

GND

40

ALARM_IN_18-

15

ALARM_IN_19-

41

ALARM_IN_20-

16

ALARM_IN_21-

42

GND

17

GND

43

ALARM_IN_22-

18

ALARM_IN_23-

44

ALARM_IN_24-

19

ALARM_IN_25-

45

GND

20

GND

46

ALARM_IN_26-

21

ALARM_IN_27-

47

ALARM_IN_28-

22

ALARM_IN_29-

48

GND

23

GND

49

ALARM_IN_30-

24

ALARM_IN_31-

50

N.C.

25

ALARM_IN_+

51

GND1

26

ALARM_IN_0-

52

GND2


Table 1-6 Alarm Output Pin Assignments 

AMP Champ Pin
Signal name
AMP Champ Pin
Signal name

1

N.C.

27

COM_0

2

COM_1

28

N.C.

3

NO_1

29

NO_2

4

N.C.

30

COM_2

5

COM_3

31

N.C.

6

NO_3

32

NO_4

7

N.C.

33

COM_4

8

COM_5

34

N.C.

9

NO_5

35

NO_6

10

N.C.

36

COM_6

11

COM_7

37

N.C.

12

NO_7

38

NO_8

13

N.C.

39

COM_8

14

COM_9

40

N.C.

15

NO_9

41

NO_10

16

N.C.

42

COM_10

17

COM_11

43

N.C.

18

NO_11

44

NO_12

19

N.C.

45

COM_12

20

COM_13

46

N.C.

21

NO_13

47

NO_14

22

N.C.

48

COM_14

23

COM_15

49

N.C.

24

NO_15

50

N.C.

25

N.C.

51

GND1

26

NO_0

52

GND2


Figure 1-17 Alarm input connector

Figure 1-18 Alarm output connector

Step 4 Complete one of the following:

If you plan to install electrical cards, continue with the "NTP-9 Install the Electrical Card Cables on the Backplane" procedure.

If you do not plan to install electrical cards, continue with the "NTP-11 Install the Rear Cover" procedure.


NTP-9 Install the Electrical Card Cables on the Backplane

Purpose

Optional EIA backplane covers are typically pre-installed when ordered with the ONS 15454. The following procedure describes how to install the electrical card cables to the backplane. If the shelf was not shipped with the correct EIA interface, you must order and install the correct EIA.

Tools/Equipment

Wire wrapper

Twisted-pair cables

BNC insertion tool

SMB cable connector

Prerequisite Procedures

NTP-5 Install the Electrical Interface Assemblies

Required/As Needed

Required if you are using electrical cards

Onsite/Remote

Onsite



Caution Always use the supplied ESD wristband when working with a powered ONS 15454. Plug the wristband cable into the ESD jack located on the lower-right outside edge of the shelf assembly.


Note Refer to the Cisco ONS 15454 Reference Manual for more information about EIAs.



Step 1 Complete the "DLP-23 Install DS-1 Cables Using Electrical Interface Adapters (Balun)" task as needed. Baluns are used on SMB EIAs to properly terminate DS-1 signals.

Step 2 To install DS-1 cables using AMP Champ cables, complete the "DLP-24 Install DS-1 AMP Champ Cables on the AMP Champ EIA" task.

Step 3 Complete the "DLP-25 Install Coaxial Cable With BNC Connectors" task as needed.

Step 4 Complete the "DLP-26 Install Coaxial Cable With High-Density BNC Connectors" task as needed.

Step 5 Complete the "DLP-27 Install Coaxial Cable with SMB Connectors" task as needed.

Step 6 Continue with the "NTP-10 Route Electrical Cables" procedure.


DLP-23 Install DS-1 Cables Using Electrical Interface Adapters (Balun)

Purpose

This task installs the DS-1 cables using the electrical interface adapters.

Tools/Equipment

Wire wrapper

Twisted-pair cables

Prerequisite Procedures

DLP-13 Install an SMB EIA

Required/As Needed

Required if you are using an SMB EIA for DS1N-14 cards

Onsite/Remote

Onsite



Note All DS-1 cables connected to the ONS 15454 DS-1 ports must terminate with twisted-pair cables to connect to the DS-1 electrical interface adapter. The DS-1 electrical interface adapters project 1.72 inches beyond the SMB EIA.



Step 1 Attach the SMB connector on an adapter to the SMB connector for the port's transmit pair on the backplane.

Step 2 Attach the SMB connector on an adapter to the SMB connector for the port's receive pair on the backplane.

Step 3 Terminate the DS-1 transmit and receive cables for the port to the wire-wrap posts on the adapter:

a. Using a wire-wrap tool, connect the receive cables to the receive adapter pins on the backplane connector for the desired port.

b. Connect the transmit cables to the transmit adapter pins on the backplane connector for the desired port.

c. Terminate the shield ground wire on the DS-1 cable to ground according to local site practice.


Note If you put DS1N-14 cards in Slots 3 and 15 to form 1:N protection groups, do not wire Slots 3 and 15 for DS-1 electrical interface adapters.


Figure 1-19 shows a ONS 15454 backplane with an SMB EIA with DS-1 electrical interface adapters attached on both sides of the shelf assembly to create DS-1 twisted-pair termination points.

Figure 1-19 A backplane with an SMB EIA for DS-1 cables

Step 4 Return to your originating procedure (NTP).


DLP-24 Install DS-1 AMP Champ Cables on the AMP Champ EIA

Purpose

This task installs the DS-1 AMP Champ cables on the AMP Champ EIA.

Tools/Equipment

Wire wrapper

Twisted-pair cables

Prerequisite Procedures

DLP-14 Install the AMP Champ EIA

Required/As Needed

Required if you are using an AMP Champ EIA for DS1N-14 cards

Onsite/Remote

Onsite



Step 1 Prepare a 56-wire cable for each DS1N-14 card you will install in the shelf assembly.

Step 2 Connect the male AMP Champ connector on the cable to the female AMP Champ connector on the ONS 15454 backplane.

Step 3 Use the clips on the male AMP Champ connector to secure the connection.

The female connector has grooves on the outside edge for snapping the clips into place.

Table 1-7 shows the pin assignments for the AMP Champ connectors on the ONS 15454 AMP Champ EIA. The shaded area corresponds to the white/orange binder group. A binder group is a set of 25 pairs of wires coded with an industry-standard color scheme.

Table 1-7 Pin Assignments for AMP Champ Connectors (Shaded Area Corresponds to White/Orange Binder Group) 

Signal/Wire
Pin
Pin
Signal/Wire
Signal/Wire
Pin
Pin
Signal/Wire

Tx Tip 1
white/blue

1

33

Tx Ring 1
blue/white

Rx Tip 1
yellow/orange

17

49

Rx Ring 1
orange/yellow

Tx Tip 2 white/orange

2

34

Tx Ring 2
orange/white

Rx Tip 2
yellow/green

18

50

Rx Ring 2
green/yellow

Tx Tip 3
white/green

3

35

Tx Ring 3
green/white

Rx Tip 3
yellow/brown

19

51

Rx Ring 3
brown/yellow

Tx Tip 4
white/brown

4

36

Tx Ring 4
brown/white

Rx Tip 4
yellow/slate

20

52

Rx Ring 4
slate/yellow

Tx Tip 5
white/slate

5

37

Tx Ring 5
slate/white

Rx Tip 5
violet/blue

21

53

Rx Ring 5
blue/violet

Tx Tip 6
red/blue

6

38

Tx Ring 6
blue/red

Rx Tip 6
violet/orange

22

54

Rx Ring 6
orange/violet

Tx Tip 7
red/orange

7

39

Tx Ring 7
orange/red

Rx Tip 7
violet/green

23

55

Rx Ring 7
green/violet

Tx Tip 8
red/green

8

40

Tx Ring 8
green/red

Rx Tip 8
violet/brown

24

56

Rx Ring 8
brown/violet

Tx Tip 9
red/brown

9

41

Tx Ring 9
brown/red

Rx Tip 9
violet/slate

25

57

Rx Ring 9
slate/violet

Tx Tip 10
red/slate

10

42

Tx Ring 10
slate/red

Rx Tip 10
white/blue

26

58

Rx Ring 10
blue/white

Tx Tip 11
black/blue

11

43

Tx Ring 11
blue/black

Rx Tip 11
white/orange

27

59

Rx Ring 11
orange/white

Tx Tip 12
black/orange

12

44

Tx Ring 12
orange/black

Rx Tip 12
white/green

28

60

Rx Ring 12
green/white

Tx Tip 13
black/green

13

45

Tx Ring 13
green/black

Rx Tip 13
white/brown

29

61

Rx Ring 13
brown/white

Tx Tip 14
black/brown

14

46

Tx Ring 14
brown/black

Rx Tip 14
white/slate

30

62

Rx Ring 14
slate/white

Tx Spare0+ Not applicable

15

47

Tx Spare0- Not applicable

Rx Spare0+ Not applicable

31

63

Rx Spare0- Not applicable

Tx Spare1+ Not applicable

16

48

Tx Spare1- Not applicable

Rx Spare1+ Not applicable

32

64

Rx Spare1- Not applicable


Table 1-8 shows the pin assignments for the AMP Champ connectors on the ONS 15454 AMP Champ EIA for a shielded DS-1 cable.

Table 1-8 Pin Assignments for AMP Champ Connectors (shielded DS1 cable) 

64-Pin Blue Bundle
64-Pin Orange Bundle
Signal/Wire
Pin
Pin
Signal/Wire
Signal/Wire
Pin
Pin
Signal/Wire

Tx Tip 1
white/blue

1

33

Tx Ring 1
blue/white

Rx Tip 1
white/blue

17

49

Rx Ring 1
blue/white

Tx Tip 2 white/orange

2

34

Tx Ring 2
orange/white

Rx Tip 2
white/orange

18

50

Rx Ring 2
orange/white

Tx Tip 3
white/green

3

35

Tx Ring 3
green/white

Rx Tip 3
white/green

19

51

Rx Ring 3
green/white

Tx Tip 4
white/brown

4

36

Tx Ring 4
brown/white

Rx Tip 4
white/brown

20

52

Rx Ring 4
brown/white

Tx Tip 5
white/slate

5

37

Tx Ring 5
slate/white

Rx Tip 5
white/slate

21

53

Rx Ring 5
slate/white

Tx Tip 6
red/blue

6

38

Tx Ring 6
blue/red

Rx Tip 6
red/blue

22

54

Rx Ring 6
blue/red

Tx Tip 7
red/orange

7

39

Tx Ring 7
orange/red

Rx Tip 7
red/orange

23

55

Rx Ring 7
orange/red

Tx Tip 8
red/green

8

40

Tx Ring 8
green/red

Rx Tip 8
red/green

24

56

Rx Ring 8
green/red

Tx Tip 9
red/brown

9

41

Tx Ring 9
brown/red

Rx Tip 9
red/brown

25

57

Rx Ring 9
brown/red

Tx Tip 10
red/slate

10

42

Tx Ring 10
slate/red

Rx Tip 10
red/slate

26

58

Rx Ring 10
slate/red

Tx Tip 11
black/blue

11

43

Tx Ring 11
blue/black

Rx Tip 11
black/blue

27

59

Rx Ring 11
blue/black

Tx Tip 12
black/orange

12

44

Tx Ring 12
orange/black

Rx Tip 12
black/orange

28

60

Rx Ring 12
orange/black

Tx Tip 13
black/green

13

45

Tx Ring 13
green/black

Rx Tip 13
black/green

29

61

Rx Ring 13
green/black

Tx Tip 14
black/brown

14

46

Tx Ring 14
brown/black

Rx Tip 14
black/brown

30

62

Rx Ring 14
brown/black

Tx Tip 15
black/slate

15

47

Tx Tip 15
slate/black

Rx Tip 15
black/slate

31

63

Rx Tip 15
slate/black

Tx Tip 16
yellow/blue

16

48

Tx Tip 16
blue/yellow

Rx Tip 16
yellow/blue

32

64

Rx Tip 16
blue/yellow


Step 4 Return to your originating procedure (NTP).


DLP-25 Install Coaxial Cable With BNC Connectors

Purpose

This task installs the coaxial cable with BNC connectors.

Tools/Equipment

None

Prerequisite Procedures

DLP-12 Install a BNC or High-Density BNC EIA

Required/As Needed

Required if you are using DS3-12, DS3XM-6, or EC-1 cards and are using a BNC interface rather than an SMB interface

Onsite/Remote

Onsite



Step 1 Place the BNC cable connector over the desired connection point on the backplane.

Figure 1-20 shows how to connect a coaxial cable to the BNC EIA using a right-angle BNC cable connector.

Figure 1-20 Using a right-angle connector to install coaxial cable with BNC connectors

Step 2 Position the cable connector so that the slot in the connector is over the corresponding notch at the backplane connection point.

Step 3 Gently push the connector down until the notch backplane connector slides into the slot on the cable connector.

Step 4 Turn the cable connector clockwise to lock it into place.

Step 5 Tie wrap or lace the cables to the EIA according to Telcordia standards (GR-1275-CORE) or local site practice.

Step 6 Route the cables to the nearest side of the shelf assembly through the side cutouts according to local site practice. The rubber coated edges of the side cutouts prevent the cables from chafing.


Warning Metallic interfaces for connection to outside plant lines (such as T1/E1/T3/E3, etc.) must be connected through a registered or approved device such as CSU/DSU or NT1.


Step 7 Label all cables at each end of the connection to avoid confusion with cables that are similar in appearance.

Step 8 Return to your originating procedure (NTP).


DLP-26 Install Coaxial Cable With High-Density BNC Connectors

Purpose

This task installs the coaxial cable with high-density BNC connectors.

Tools/Equipment

BNC insertion tool

Prerequisite Procedures

DLP-12 Install a BNC or High-Density BNC EIA

Required/As Needed

Required if you are using DS3-12, DS3XM-6, or EC-1 cards and are using a BNC interface rather than an SMB interface

Onsite/Remote

Onsite



Step 1 Place the cable connector over the desired connection point on the backplane.

Step 2 Using the BNC insertion tool, position the cable connector so that the slot in the connector is over the corresponding notch at the backplane connection point.

Step 3 Gently push the connector down until the notch backplane connector slides into the slot on the cable connector.

Step 4 Turn the cable connector clockwise to lock it into place.

Step 5 Tie wrap or lace the cables to the EIA according to Telcordia standards (GR-1275-CORE) or local site practice.

Step 6 Route the cables to the nearest side of the shelf assembly through the side cutouts according to local site practice.


Warning Metallic interfaces for connection to outside plant lines (such as T1/E1/T3/E3, etc.) must be connected through a registered or approved device such as CSU/DSU or NT1.

The rubber coated edges of the side cutouts prevent the cables from chafing.

Step 7 Return to your originating procedure (NTP).


DLP-27 Install Coaxial Cable with SMB Connectors

Purpose

This task installs the coaxial cable with SMB connectors. Refer to Figure 1-21 when performing task.

Tools/Equipment

SMB cable connector

Prerequisite Procedures

DLP-13 Install an SMB EIA

Required/As Needed

Required if you are using DS3-12, DS3XM-6, or EC-1 cards and are using an SMB interface rather than a BNC interface

Onsite/Remote

Onsite



Step 1 Place the SMB cable connector over the desired connection point on the backplane.

Step 2 Gently push the connector until it clicks into place.

Step 3 Tie wrap or lace the cables to the EIA according to Telcordia standards (GR-1275-CORE) or local site practice.

Step 4 Route the cables to the nearest side of the shelf assembly into rack runs according to local site practice.

Figure 1-21 Installing coaxial cable with SMB connectors


Warning Metallic interfaces for connection to outside plant lines (such as T1/E1/T3/E3, etc.) must be connected through a registered or approved device such as CSU/DSU or NT1.

Step 5 Label the transmit, receive, working, and protect cables at each end of the connection to avoid confusion with cables that are similar in appearance.

Step 6 Return to your originating procedure (NTP).


NTP-10 Route Electrical Cables

Purpose

The following procedure explains how to route and manage electrical (backplane) cables.

Tools/Equipment

RG179, RG59 (735A) 26 AWG cable, or RG59 (734A) 20 AWG cable

Prerequisite Procedures

NTP-9 Install the Electrical Card Cables on the Backplane

Required/As Needed

Required if using electrical cards

Onsite/Remote

Onsite



Step 1 To route coaxial cables, complete the "DLP-28 Route Coaxial Cables" task.

Step 2 To route DS-1 twisted pair cables, complete the "DLP-29 Route DS-1 Twisted-Pair Cables" task.

Step 3 Continue with the "NTP-11 Install the Rear Cover" procedure.


DLP-28 Route Coaxial Cables

Purpose

This task routes the coaxial cables.

Tools/Equipment

RG179, RG59 (735A) 26 AWG cable, or RG59 (734A) 20 AWG cable

Prerequisite Procedures

DLP-25 Install Coaxial Cable With BNC Connectors

DLP-26 Install Coaxial Cable With High-Density BNC Connectors

DLP-27 Install Coaxial Cable with SMB Connectors

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Tie wrap or lace the coaxial cables according to local site practice and route the cables through the side cutouts on either side of the ONS 15454. The rubber coated edges of the side cutouts prevent the cables from chafing.

Step 2 Use short lengths of "pigtail" RG179 to terminate the shelf assembly.

Step 3 Use standard RG59 (735A) cable connected to the RG179 for the remainder of the cable run. When using a 10-foot section of the RG179, you can attach a maximum length of 437 feet of RG59 (735A). When using a 30-foot section of RG179, you can attach a maximum length of 311 feet of RG59 (735A).

When using the RG179 cable, the maximum distance available (122 feet) is less than the maximum distance available with standard RG59 (735A) cable (306 feet). The maximum distance when using the RG59 (734A) cable is 450 feet. The shorter maximum distance available with the RG179 is due to a higher attenuation rate for the thinner cable. Attenuation rates are calculated using a DS-3 signal:

For RG179, the attenuation rate is 59 dB/kft @ 22 MHz.

For RG59 (735A), the attenuation rate is 23 dB/kft @ 22 MHz.

Use a figure of 5.0 for total cable loss when making calculations. Figure 1-22 shows an example of proper coaxial cable routing.

Figure 1-22 Routing coaxial cable (SMB EIA backplane)

Step 4 Return to your originating procedure (NTP).


DLP-29 Route DS-1 Twisted-Pair Cables

Purpose

This task routes the DS-1 twisted-pair cables.

Tools/Equipment

None

Prerequisite Procedures

DLP-23 Install DS-1 Cables Using Electrical Interface Adapters (Balun)

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Verify the following:

DS-1 electrical interface adapters are installed on every transmit and receive connector for DS-1 ports.

Wire-wrap posts on the DS-1 electrical interface adapters are used to connect the terminated incoming cables.

Step 2 Tie-wrap or lace the twisted-pair cables according to local site practice and route the cables into the side cutouts on either side of the ONS 15454.


Note SMB EIAs feature cable-management eyelets for tie wrapping or lacing cables to the cover panel.


Step 3 Return to your originating procedure (NTP).


NTP-11 Install the Rear Cover

Purpose

The following procedure explains how to install the rear cover.

Tools/Equipment

#2 Phillips screwdriver

Medium slot head screwdriver

Small slot head screwdriver

Prerequisite Procedures

None

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Locate the three screws that run vertically along both edges of the backplane ( Figure 1-23).

Figure 1-23 Backplane attachment for the rear cover


Tip Only six screws (three on each side) line up with the screw slots on the mounting brackets, making the screws easy to locate.


Step 2 Loosen the top and bottom screws on one edge of the backplane to provide room to slide the mounting brackets into place using the u-shaped screw slots on each end.

Step 3 Slide one of the mounting brackets into place and tighten the screws.

Step 4 Repeat Steps 2 and 3 for the second mounting bracket.

Step 5 Attach the cover by hanging it from the mounting screws on the back of the mounting brackets and pulling it down until it fits snugly into place.

Figure 1-24 shows rear cover installation using spacers.

Figure 1-24 Installing the rear cover with spacers

Step 6 Continue with the "NTP-12 Install Ferrites" procedure.


NTP-12 Install Ferrites

Purpose

This procedure describes how to attach ferrites.

Tools/Equipment

Oval and/or block ferrites

Prerequisite Procedures

NTP-6 Install the Power and Ground

NTP-8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

Required/As Needed

As needed

Onsite/Remote

Onsite



Step 1 To attach ferrites to power cabling, complete the "DLP-30 Install Ferrites to Power Cabling" task.

Step 2 To attach ferrites to wire-wrap pin fields, complete the "DLP-31 Attach Ferrites to Wire-Wrap Pin Fields" task.

Step 3 Continue with the "NTP-13 Perform the Shelf Installation Acceptance Test" procedure.


DLP-30 Install Ferrites to Power Cabling

Purpose

This task attaches ferrites to power cabling. Use a single oval ferrite TDK ZCAT2035-0930 and/or one block ferrite Fair Rite 0443164151 for each pair of cables, depending on the EIA.

Tools/Equipment

Oval and/or block ferrites

Prerequisite Procedures

None

Required/As Needed

As needed

Onsite/Remote

Onsite



Step 1 If you are using block ferrites, wrap the cables once around and through the block ferrites.

Step 2 If you are using oval ferrites, pull the cable straight through the oval ferrites.


Note If you are using both block and oval ferrites, place the oval ferrite between the ONS 15454 and the block ferrite as shown in Figure 1-25.



Note Place the oval ferrite as close to the power terminals as possible and place the block ferrite within 5 to 6 inches of the power terminals.


Figure 1-25 Attaching block and oval ferrites to power cabling

Step 3 Return to your originating procedure (NTP).


DLP-31 Attach Ferrites to Wire-Wrap Pin Fields

Purpose

This task attaches ferrites to wire-wrap pin fields. Use an oval ferrite TDK ZCAT1730-0730 and block ferrite Fair Rite 0443164151 for each pair of cables. Figure 1-26 shows the suggested method for attaching ferrites to wire-wrap pin fields.

Tools/Equipment

Oval and block ferrites

Prerequisite Procedures

NTP-8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

Required/As Needed

As needed

Onsite/Remote

Onsite



Step 1 Wrap the cables once around and through the block ferrites and pull the cables straight through the oval ferrites.

Step 2 Place the oval ferrite as close to the wire-wrap pin field as possible and between the ONS 15454 and the block ferrite as shown. The block ferrite should be within 5 to 6 inches of the wire-wrap pin field.

Figure 1-26 Attaching ferrites to wire-wrap pin fields

Step 3 Return to your originating procedure (NTP).


NTP-13 Perform the Shelf Installation Acceptance Test

Purpose

Use this procedure to perform a shelf installation acceptance test.

Tools/Equipment

Voltmeter

Tools/Equipment

Oval and/or block ferrites

Prerequisite Procedures

Applicable procedures in Chapter 1

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Complete Table 1-9 by verifying that each procedure was completed.

Table 1-9 ONS 15454 Shelf Installation Task Summary 

Description
Completed

NTP-1 Unpack and Inspect the ONS 15454 Shelf Assembly

 

NTP-2 Install the Shelf Assembly

 

NTP-3 Open and Remove the Front Door

 

NTP-4 Remove the Backplane Covers

 

NTP-5 Install the Electrical Interface Assemblies

 

NTP-6 Install the Power and Ground

 

NTP-7 Install the Fan-Tray Assembly

 

NTP-119 Install the Alarm Expansion Panel

 

NTP-8 Install Wires to Alarm, Timing, LAN, and Craft Pin Connections

 

NTP-120 Install an External Wire-Wrap Panel to the AEP

 

NTP-9 Install the Electrical Card Cables on the Backplane

 

NTP-10 Route Electrical Cables

 

NTP-11 Install the Rear Cover

 

NTP-12 Install Ferrites

 

Step 2 Complete the "DLP-32 Inspect the Shelf Installation and Connections" task.

Step 3 Complete the "DLP-33 Measure Voltage" task.

Step 4 Continue with the "NTP-15 Install the Common Control Cards" procedure on page 2-2.


DLP-32 Inspect the Shelf Installation and Connections

Purpose

This task inspects the shelf installation and connections to verify everything is installed and connected properly.

Tools/Equipment

None

Prerequisite Procedures

Complete Table 1-9.

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Check each wire and cable connection to make sure all cables are locked securely. If a wire or cable is loose, return to the appropriate procedure in this chapter to correct it.

Step 2 To check that the backplane is seated correctly, verify that the screw holes and the backplane interface card holes align properly and that the A and B connectors interlock.

Step 3 Return to your originating procedure (NTP).


DLP-33 Measure Voltage

Purpose

This task measures the power to verify correct power and returns.

Tools/Equipment

Voltmeter

Prerequisite Procedures

Complete Table 1-9.

Required/As Needed

Required

Onsite/Remote

Onsite



Step 1 Using a voltmeter, verify the office ground and power ( Figure 1-9 shows the power terminals):

a. Place the black lead (positive) on the frame ground on the bay. Hold it there while completing
Step b.

b. Place the red lead (negative) on the fuse power points and alarm panel to verify that they read between -42 VDC and -57 VDC (power) and 0 (return ground).

Step 2 Using a voltmeter, verify the shelf ground and power wiring:

a. Place the black lead (positive) on the RET1 and the red lead on the BAT1 point. Verify a reading between -42 VDC and -57 VDC. If there is no voltage, check the following:

Battery and ground reversed to the shelf

Battery is open or missing

Return is open or missing

b. Repeat Step 2 for the RET2 and BAT2 if the B power feed is provided.

Figure 1-27 ONS 15454 power terminals

Step 3 Return to your originating procedure (NTP).



hometocprevnextglossaryfeedbacksearchhelp

Posted: Fri Feb 22 14:34:12 PST 2008
All contents are Copyright © 1992--2008 Cisco Systems, Inc. All rights reserved.
Important Notices and Privacy Statement.