|
This chapter describes and illustrates how to cable the DC fuse panels in the Cisco AccessPath-TS3 Model 530 Integrated Access System. The DC fuse panels are factory-installed.
The DC fuse panels accept two 50 amp, -48 VDC circuits of input power. Each panel can supply a total of 100 amps of steady-state output current.
Note Your DC fuse panel might look slightly different, but its functionality is the same as the panel described and illustrated below. Grey fuse panels have circuit breakers; black do not.
Before working on equipment that is connected to power lines, remove jewelry (including rings, necklaces, and watches). Metal objects will heat up when connected to power and ground and can cause serious burns or weld the metal object to the terminals.
The following steps explain how toconnect the internal power supplies to the DC fuse panels:
Step 2 Cut sets of wires (1 red, 1 black) to the lengths specified in Step 7 through Step 11.
Note Red wires are positive (+) and black wires are negative (-).
Step 3 Remove about 0.25 inch of insulation from each end of the wire.
Step 4 Tin both ends to insure that the wire does not fray or cause a bad connection.
Step 5 Connect a spade-type terminal lug to the end of each wire, as necessary.
The wires to the Access Server Shelf, System Controller and the Router Shelf (or shelves) do not require terminal lugs at the shelf end of the wires.
Step 6 The following steps explain how to connect each shelf (see Figure 3-2).
Note Your DC fuse panel might look slightly different, but its functionality is the same as the panel described and illustrated below. Grey fuse panels have circuit breakers; black do not.
Step 7 Wire the System Controller (also called the Console Management Shelf) as follows:
DC Power Termination | DC Fuse Panel and Terminal | 14 gauge wire spec |
---|---|---|
Step 8 Wire the Switch Shelf as follows:
Step 9 Wire the first Router Shelf as follows. The first Router Shelf is the lower of the 2 router shelves.
Step 10 Wire the second Router Shelf as follows. The second Router Shelf is the upper of the 2 router shelves.
Step 11 Wire the Access Server Shelf as follows:
DC Power Termination | DC Fuse Panel and Terminal | 14 gauge wire spec |
---|---|---|
Access Server Shelf 1 (AS1) | ||
Access Server Shelf 2 (AS2) | ||
Access Server Shelf 3 (AS3) | ||
Access Server Shelf 4 (AS4) | ||
Access Server Shelf 5 (AS5) | ||
Access Server Shelf 6 (AS6) | ||
Access Server Shelf 7 (AS7) | ||
Access Server Shelf 8 (AS8) | ||
Access Server Shelf 9 (AS9) | ||
Access Server Shelf 10 (AS10) | ||
Access Server Shelf 11 (AS11) |
The following steps explain how toconnect input power to the DC fuse panels:
You must secure the fuse panel frame ground to the frame ground stud on the system rack. Use a green 6-gauge wire to connect a ground to the frame ground stud at the top (or bottom) right rear corner of the system rack. The frame ground should be grounded at the main input to the system system.
A readily accessible two-pole disconnect device must be incorporated in the fixed wiring.
Step 2 Confirm that every AccessPath shelf is properly grounded.
Step 3 Connect the 14 AWG green ground wires from the earthing terminal of each shelf to the tap angles:
(a). For each shelf, cut a 10 in. length of 14 AWG wire.
(b). Remove 0.25 inch of insulation from the end of the 14 AWG wire.
(c). Double-crimp a ring-lug to an end of the wire and connect it to the tap angle at the right of each shelf using a screw and lock washer.
(d). Ground each shelf by securing the other end of its grounding wire to the earthing terminal of the shelf.
Step 4 Confirm that the main power circuit breakers are OFF at the building feed; lockouts are mandatory.
Step 5 Confirm that the 2 main circuit breakers on the DC fuse panel are in the OFF position. The switches point away from each other in the OFF position.
Note The grey DC fuse panels have input circuit breakers and black panels do not.
Step 6 Cut 2 sets of 6-gauge wires (2 white, 2 black) to the lengths necessary to reach the DC power source from the DC fuse panels when they are mounted in the system rack.
Note White wires are positive (+) and black wires are negative (-).
Step 7 Remove 0.5 inch of insulation from the end of each wire.
Step 8 Remove the DC input terminal connectors on the rear panel by first removing the plastic safety shield, then loosening both locking nuts on each connector.
Step 9 Solder the uninsulated end of each wire into the terminal connector so that no bare wire is exposed.
Step 10 Replace the terminals on the appropriate connectors on the DC fuse panels and tighten both locking nuts, as shown in Figure 3-3.
Note Your DC fuse panel might look slightly different, but its functionality is the same as the panel described and illustrated below. Grey fuse panels have circuit breakers; black do not.
Step 11 Replace the plastic safety shield that covers the DC input connectors.
Step 12 After connecting 2 sets of input feed wires to each of the DC fuse panels, connect each set of 50-amp input feed connections to the DC power source. Confirm that the polarity of all connections is correct.
The following steps explain how toinstall the correct fuses in the correct positions:
Note The grey DC fuse panels have input circuit breakers and black panels do not.
Step 2 Install individual GMT-style fuses as listed in Table 3-1 DC Fuse Panel Fuse Locations and Sizes to protect the system at the component level.
Note Your DC fuse panel might look slightly different, but its functionality is the same as the panel described and illustrated below. Grey fuse panels have circuit breakers; black do not.
Step 3 Verify that you installed GMT-style fuses of the correct rated current in the correct locations, as specified in Table 3-1.
Step 4 After installing all the fuses correctly, continue with the procedure "Powering On the System."
AccessPath Shelf Location | DC Fuse Panel and Terminal | Fuse Size |
---|---|---|
The following steps explain how to power on the system:
Step 2 Confirm that the 2 main circuit breakers on each of the DC fuse panels are in the OFF position. The switches point away from each other in the OFF position.
Note The grey DC fuse panels have input circuit breakers and the black do not.
Step 3 Confirm that the main power feeds to the DC fuse panels are the correct polarity.
Step 4 Confirm that all connections from the DC fuse panels to the DC power supplies are the correct polarity.
Step 5 Turn on all DC power supplies at the component level.
Step 6 Go to the main circuit breakers off the input feeds and place the circuit breakers in the ON position.
Step 7 Turn on both of the DC fuse panel Main Power A circuit breakers.
Note The grey DC fuse panels have input circuit breakers and the black do not.
Step 8 Turn on the DC fuse panel Main Power B circuit breaker on panel 1 only.
Step 9 Check the power supples and systems for power-on LED indications and airflow. Make this visual check inside the cabinet on each power supply and each system.
If a power system failure occurs, one or more DC fuses will open. In case of multiple failures, one or both of the main circuit breakers will trip, shutting down several units in the system system if not the entire system.
Note The grey DC fuse panels have input circuit breakers and the black do not.
The following steps explain how to troubleshoot the system:
When equipment installed in an system system rack fails because of overheating or power loss, try operating the equipment by itself. Power OFF other equipment in the rack (and in adjacent racks) to allow the failing unit maximum cooling air and clean power.
Step 2 Replace any defective fuse with a fuse of the correct rating.
Step 3 Follow the power-on sequence of operations. See "Powering On the System".
Step 4 Verify that the proper LED power on indications are present and that airflow has resumed.
Cisco Connection Online (CCO) is Cisco Systems' primary, real-time support channel. Maintenance customers and partners can self-register on CCO to obtain additional information and services.
Available 24 hours a day, 7 days a week, CCO provides a wealth of standard and value-added services to Cisco's customers and business partners. CCO services include product information, product documentation, software updates, release notes, technical tips, the Bug Navigator, configuration notes, brochures, descriptions of service offerings, and download access to public and authorized files.
CCO serves a wide variety of users through 2 interfaces that are updated and enhanced simultaneously: a character-based version and a multimedia version that resides on the World Wide Web (WWW). The character-based CCO supports Zmodem, Kermit, Xmodem, FTP, and Internet e-mail, and it is excellent for quick access to information over lower bandwidths. The WWW version of CCO provides richly formatted documents with photographs, figures, graphics, and video, as well as hyperlinks to related information.
You can access CCO in the following ways:
For a copy of CCO's Frequently Asked Questions (FAQ), contact cco-help@cisco.com. For additional information, contact cco-team@cisco.com.
Note If you are a network administrator and need personal technical assistance with a Cisco product that is under warranty or covered by a maintenance contract, contact Cisco's Technical Assistance Center (TAC) at 800 553-2447, 408 526-7209, or tac@cisco.com. To obtain general information about Cisco Systems, Cisco products, or upgrades, contact 800 553-6387, 408 526-7208, or cs-rep@cisco.com.
Posted: Tue Jan 21 04:31:57 PST 2003
All contents are Copyright © 1992--2002 Cisco Systems, Inc. All rights reserved.
Important Notices and Privacy Statement.