Acceptance Test Plan

This chapter contains tables and checklists to use during the first turn up and test of a Cisco ONS 15200 system. When you are performing the turn up and test procedures in "Turn Up and Test," you are asked to complete the tables in this appendix to prepare for customer acceptance of the ONS 15200 system.

A.1 ONS 15200 Network Configuration

A.2 ONS 15252 Multichannel Unit Turn Up and Test


Note   The expected minimum and maximum transmit power is provided by your network planner. Actual transmit power must be within the range provided by your network planner.

A.3 ONS 15201 Single-Channel Unit Turn Up and Test